Ohio Admin. Code 153:1-4-02 - Type and amount of surety bonds
(A) Prior to the execution of the contract,
the construction manager at risk or design-build firm shall provide the public
authority with separate performance and payment bonds. The penal sum of each
bond shall equal one hundred per cent of the contract sum .
(B) If the contract sum increases at any time
after the construction manager at risk or design-build firm provides surety
bonds in accordance with paragraph (A) of this rule, the construction manager
at risk or design-build firm shall cause the penal sum of each surety bond to
be increased as necessary to maintain compliance with paragraph (A) of this
rule. The delivery of written consent from the affected surety or sureties to
the public authority by the construction manager at risk or design-build firm
confirming the increased penal sums is a condition precedent to the public
authority's obligation to pay the construction manager at risk or design-build
firm for any portion of the work associated with the increase in the contract
sum .
(C) If at any time prior to
final payment to the construction manager at risk or the design-build firm, any
surety providing a surety bond for the project (1) is adjudged bankrupt or has
made a general assignment for the benefit of its creditors; (2) has liquidated
all assets or has made a general assignment for the benefit of its creditors;
(3) is placed in receivership; (4) otherwise petitions a state or federal court
for protection from its creditors; or (5) allows its license to do business in
Ohio to lapse or to be revoked, then the construction manager at risk or the
design-build firm shall, within twenty-one days of any such action listed
above, provide the public authority with new surety bonds in the form and
amount described in the applicable subdivision of these rules. The delivery to
the public authority by the construction manager at risk or design-build firm
of replacement surety bonds is a condition precedent to the public authority's
obligation to make any payment to the construction manager at risk or
design-build firm.
(D) The public
authority shall require the construction manager at risk or the design-build
firm to submit a separate performance bond and a separate payment bond using
the 2012 edition of "Document 00 61 13.13 -
Performance Bond Form" and "Document 00 61 13.16 - Payment Bond Form." These
forms may be
"Performance Bond Form" and
"Payment Bond Form" found on the website of the
office of the state architect in the department of
administrative services
Ohio facilities
construction commission under either CM at Risk
or Design-Build: standard requirements for
public facility construction:
http://das.ohio.gov/Divisions/GeneralServices/StateArchitectsOffice/ListofStandard RequirementsDocuments.aspx
http://ofcc.ohio.gov/Documents/AgreementsandStandardRequirements.aspx.
Any bond submitted under this rule shall name as obligee the public authority
or the state, as applicable.
Notes
Promulgated Under: 119.03
Statutory Authority: 9.333(B), 153.70(C)
Rule Amplifies: 9.333, 153.70
Prior Effective Dates: 12/26/2011, 01/13/2017
Promulgated Under: 119.03
Statutory Authority: 9.333(B), 153.70(C)
Rule Amplifies: 9.333, 153.70
Prior Effective Dates: 12/26/2011
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.