(A)
Clean hard fill consisting of reinforced or nonreinforced concrete, asphalt
concrete, brick, block, tile, or stone shall be managed in one or more of the
following ways:
(1) Recycled into a usable
construction material.
(2) Disposed
in licensed construction and demolition debris or other waste
facilities.
(3) Used in legitimate
fill operations for construction purposes or to bring the site up to a
consistent grade, on the site of generation.
(4) Used in legitimate fill operations for
construction purposes or to bring the site up to a consistent grade, on a site
other than the site of generation, pursuant to paragraph (C) of this rule.
[Comment: Use of clean hard fill may
could create a
nuisance or a safety hazard. The application of cover over the clean hard fill
may be one way to address the nuisance or safety hazard.]
(B) Clean hard fill may be stored
for a period of less than two years. For the purpose
purposes of
this rule, "stored" means debris which
that is held in a manner remaining retrievable and
substantially unchanged. Clean hard fill stored for more than two years shall be considered illegal
disposal of construction and demolition debris. However, clean hard fill piled adjacent to a construction
materials processing facility shall not be considered stored for more than two
years if the pile is active, that is, if clean hard fill material is added to
and removed from the pile within a two year period.
(C) The person responsible for causing clean
hard fill to be used in legitimate fill operations for construction purposes or
to bring the site up to a consistent grade, on a site other than the site of
generation, shall provide a written "Notice of Intent to Fill" to each
licensing authority where the clean hard fill is to be placed. The "Notice of
Intent to Fill" shall state the nature of the fill material, the site to be
filled, when filling will begin and end, and the telephone number of the
notifier. The notification shall be received by each local licensing authority
with sites to be filled, at least seven days prior to filling as
required by
specified in division (F) of section
3714.13 of the Revised Code. The
notifier shall provide a new " Notice of Intent
to Fill" if there are any changes in the
information required by
specified in this rule for notification.
Notes
Promulgated Under: 119.03
Statutory Authority: 3714.02
Rule Amplifies: 3714.02, 3714.04, 3714.06
Prior Effective Dates: 09/30/1996, 08/31/2002, 04/17/2015
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.