Okla. Admin. Code § 35:17-3-25 - Closure of swine waste retention structures
(a) If for any reasona waste retention
structure is taken out of operation permanently or by action of the State Board
of Agriculture is ordered to permanently cease operations, the owner is
responsible fornotifying the Department of owner's intention to close the waste
retention structures for the handling of animal waste. The owner is responsible
for the proper closure of all waste retention structures to be closed. If a
facility temporarily ceases operations and remains in full compliance with its
Pollution Prevention Plan, the facility shall not be considered to have
permanently closed.
(b) The owner
shall submit a closure plan as part of the permit application including at a
minimum:
(1) The sequence of closing process
including but not limited to handling of waste retention structure wastewater,
solids, and handling and safe disposal of bottom sludge.
(2) Demonstrate the availability of
sufficient land area for land application of the liquid, solid, and sludge
component of the waste retention structure.
(3) Provide a copy of a written estimate, in
current dollars, of the cost of hiring an independent third party to
decommission each waste retention structure.
(c) All future changes or modifications to
the closure plan shall be approved by the Department.
(d) A post closure monitoring program shall
be conducted for a period of at least three (3) years.
(e) A certificate of post closure performance
shall be submitted to the Department at the end of the post closure period. The
certificate shall be signed by the owner and by a Professional Engineer
registered in the State of Oklahoma, indicating that all waste retention
structures were maintained and monitored in accordance with the approved
closure plan.
(f) Closure
requirements of waste retention structures shall be based on site specific
conditions, as follows:
(1) The Department
shall be notified in writing whenever a swine waste retention structure becomes
permanently inactive, is abandoned, or operation of the structure ceases
permanently for any reason. Any swine waste retention structure shall be
considered by the Department to havebecome permanently inactive or to have
ceased operations permanently in the following circumstances:
(A) The facility is closed by the Department
because of repeated violations which result in the filing of a Board order to
cease operations.
(B) The owner is
unable to furnish documentation to show that there has been receipt of swine
waste into the retention structure during the previous twenty-four (24) months
and the owner is not maintaining the retention structure in consistent
compliance with the applicable rules and the Department approved
plans.
(2) Upon the
owner's determination that a swine waste retention structure has become
permanently inactive or has permanently ceased operation the owner shall notify
the Department in writing within ninety (90) calendar days thereafter of the
intention to close swine waste retention structures. Closure of retention
structures shall commence within six (6) months of the date of notice to the
Department of the intention to close and be completed withintwo (2) subsequent
growing seasons. Closure shall be in accordance with a closure plan approved by
the Department. Any extension of time for closure shall be requested in writing
by the owner and approved by the Department. A legal change other than a
transfer of the owner of any swine waste retention structure shall not extend
the time limit for closure.
(3)
Liquid contents of a waste retention structure may be pumped out and land
applied according to Department rules.
(4) Solids from the waste retention structure
shall be removed and disposed of in an environmentally safe manner.
(5) Sludge from the bottom of the waste
retention structure shall be removed without compromising the integrity of the
liner. Sludge may be land applied according to Department rules.
(6) The owner shall grid sample soil from the
bottom of the waste retention structure and, at the owner's election, shall
either:
(A) have the samples analyzed in a
State certified laboratory for nitrate-nitrogen and electrical conductance;
or
(B) analyze samples in the field
for nitrate-nitrogen and electrical conductance using field leaching procedures
and a test kit, with laboratory confirmation by sending one sample per every
twenty (20) samples to a laboratory for analysis.
(7) Owner shall develop a plan, subject to
Department approval, regarding soil removal, if necessary, based on the grid
sample data.
(8) If soil is to be
removed from the bottom of a waste retention structure, it shall be managed in
an environmentally safe manner approved by the Department. Management options
may include, but are not limited to, land application , disposal, and
reuse.
(9) The Department may
require monitoring wells if evidence indicates that contamination has migrated
to the groundwater based on site specific conditions.
(10) Exemption from closure and transfer of
responsibility for any swine waste retention structure to any other party shall
be requested in writing for approval by the Department.