Or. Admin. R. 123-027-0161 - Non-Federal Project Application Review and Approval
To approve an application for assistance from the fund, the Authority must make the determinations as follows:
(1) The project is an eligible project. If
the Authority determines that the project is not eligible, it may reject an
application or require further documentation from the Port;
(2) The requisite need for the project has
been demonstrated to the Authority in the application or the local planning
process;
(3) If application is for
a loan, the loan security includes the pledge of revenues and/or other funds,
and is sufficient, when considered with other security, to assure
repayment;
(4) The Port is willing
and able to enter into a contract with the Authority; and
(5) Moneys in the fund are or will be
available for the project.