Or. Admin. R. 123-027-0166 - Non-Federal Project Award and Funding
(1) The Authority and the Port will execute a
contract prior to disbursal of moneys from the Fund. The contract will be in a
form and content as provided by the Authority.
(a) Payments from the fund will be disbursed
in accordance with the executed contract.
(b) The Port must provide the Authority with
written reports, records, and an accounting of detailed costs for a project as
described in the contract.
(2) All eligible projects may be awarded loan
funding of up to 100% of the total project cost, or for the required local
match, under the following terms:
(a) Interest
rates will be determined by Authority at time of award, according to Authority
policy; and
(b) The loan term will
not exceed 25 years.
(3)
If the Authority determines 100% loan funding is not feasible due to the
financial hardship of the port, grants may be awarded if Authority determines
at least one of the following circumstances exists:
(a) Job creation and/or retention will be a
direct result of the project;
(b)
There is an urgent need for environmental remediation and the Authority's
financial analysis determines that the Port's borrowing capacity is
insufficient to finance the project;
(c) The project deals with critical public
safety issues and the Authority's financial analysis determines that the Port's
borrowing capacity is insufficient to finance the project; or
(d) There is imminent threat that the Port
will lose any applicable permits and the Authority's financial analysis
determines that the Port's borrowing capacity is insufficient to finance the
project.
(e) The Authority's
financial analysis determines that the project cannot proceed without a
grant.
(4) Projects
eligible due to the provisions of subsection 0106 may be awarded grant funding
up to 75 percent of the project cost. A 25 percent local match is required.
In-kind services from the Port may be no more than 10 percent of the total
project cost.
(5) The Port must
secure, and be able to provide upon request, a land use compatibility statement
from the appropriate jurisdiction(s) for the project.
(6) Any amount disbursed from the Fund and
not used for a project must be returned to the Authority.