Or. Admin. R. 123-650-4000 - DESIGNATIONS AND BOUNDARY CHANGES - Initiating Designation
To designate or re-designate an enterprise zone under ORS 285C.065 or 285C.250:
(1) The process begins with the Sponsoring
Government(s) sending a formal advisory to the Department of its intent to
re-/designate. This may happen at any time for a new designation, but for
concurrent re-designation, the local zone sponsor shall timely provide the
advisory under ORS
285C.074
after January 1 (but by May 16 at the very latest), preceding July 1 when the
existing zone will have Terminated-by-Statute.
(2) The Department will respond promptly to
such an advisory, which if by telephone will be memorialized at least through
email, consulting with the Sponsoring Government(s) about:
(a) The utility, impacts and responsibilities
of re-/designating and having an enterprise zone;
(b) Steps to re-/designate a zone, including
but not limited to formally sending notice to and consulting with local taxing
districts, after this consultation by the Department has taken place;
(c) Documentation, as well as sample
resolution language, needing to be submitted to the Department;
(d) Economic hardship criteria and possible
assistance in identifying measures for the local area;
(e) Prohibitions in OAR 123-650-4900(2);
and
(f) Other matters as
appropriate or necessary.
(3) Not less than 45 days after advising the
Department, the Sponsor Governments may submit the enterprise zone
re-/designation, as described in OAR 123-650-4100 (electronically as
desired).
Notes
Statutory/Other Authority: ORS 285A.075, 285C.060(1) & 285C.067(2)
Statutes/Other Implemented: ORS 285C.065, 285C.067, 285C.074, 285C.078 & 285C.250