Or. Admin. R. 141-010-0230 - Permit Review Process
(1)
Within ten working days after receipt of a completed application, the
Department shall:
(a) Circulate the
application for review and comment to:
(A) The
Department of Fish and Wildlife;
(B) The Department of Geology and Mineral
Industries;
(C) The Department of
Land Conservation and Development;
(D) The State Historic Preservation
Officer;
(E) Any other state agency
the director determines may be affected by the proposed survey.
(b) Provided written notice of the
application to:
(A) The governing body of each
county within the proposed survey region;
(B) Any person who has requested notice from
the director of permit applications;
(C) The general public, by publication once
in a newspaper of general circulation in the region proposed for
survey.
(2)
Comment by state agencies:
(a) Within ten
working days after the date an application is circulated by the Department, a
state agency may request the Department, to obtain additional information from
the applicant. The Department shall forward the request to the applicant and
shall forward a copy of the response to the requesting agency;
(b) When additional information is requested,
the agency shall have 20 working days after the date the additional information
is forwarded by the Department in which to submit written comments and
recommendations for permit conditions, if any;
(c) When additional information is not
requested, the agency shall have 20 working days after the date the application
is circulated in which to submit written comments and recommendations for
permit conditions, if any.
(3) Comment by other than state agencies:
(a) Persons other than state agencies shall
have 30 days after the date of notice of the application in which to submit
written comments to the Department;
(b) Within 15 days of publication of the
notice, as required in subsection (1)(b)(C), any person may request a public
hearing on the application. A request for hearing shall be submitted to the
director, in writing. The director shall have discretion to decide whether a
public hearing shall be held. If held, the public hearing shall take place
within 15 days of receipt of the written request. The director shall provide
appropriate public notice of the hearing.
(4) Within 20 working days from the close of
the comment periods provided in section (3) of this rule, the Department shall:
(a) Review the comments;
(b) Take action on the application request;
and
(c) Give written notice of the
action to the applicant and each state agency and person who has submitted
written comments on the application.
(5) Within ten working days of the date of
notice of action on the application, the applicant or any aggrieved person may
request a hearing from the director:
(a) The
request shall be in writing and shall state the specific nature of the
objection;
(b) When requested by
the applicant, the hearing shall be scheduled within 45 days of the written
request;
(c) When requested by a
person other than the applicant, the director shall have discretion to decide
whether a hearing shall be held. If held, the hearing shall take place within
45 days of receipt of the request. The applicant shall have the opportunity to
participate as a party in the hearing;
(d) The hearing shall be conducted as a
contested case hearing and shall be subject to the applicable provisions of ORS
183.413 -
183.497;
(e) A final order shall be issued by the
director within 20 working days of the close of the hearing record.
Notes
Stat. Auth.: ORS 274
Stats. Implemented: ORS 274 .735