Or. Admin. R. 141-083-0830 - Cable Easement Application Requirements
(1) Any person wanting to place a cable in
the Territorial Sea shall obtain an easement from the Division, and approval by
the Land Board.
(2) Unless
otherwise allowed by the Director, a fully completed application for an
easement shall be submitted to the Division at least one-hundred and eighty
(180) days prior to placement of any part of the cable or construction of any
associated landing-related facility or equipment on state-owned submerged and
submersible land within the Territorial Sea. Each application for a cable
easement shall be accompanied by a non-refundable application processing fee
payable to the Division in the amount indicated in OAR 141-083-0830(3) of these
rules.
(3) Each application for a
cable easement crossing the Territorial Sea shall be accompanied by a
non-refundable deposit payable to the Division in the amount of five thousand
dollars ($5,000).
(4) Should the
Division, in consultation with the applicant and other interested parties,
determine that it is necessary to conduct environmental or other studies
necessary to assist in evaluating the project's compliance with the
requirements of Statewide Planning Goal 19 and the Territorial Sea Management
Plan, the applicant shall be directly responsible for retaining and paying for
the requisite studies.
Notes
Stat. Auth.: ORS 196.800 - ORS 196.990 & ORS 390.805 - ORS 390.925
Stats. Implemented: ORS 196.800 - ORS 196.990 & ORS 390.805 - ORS 390.925