Or. Admin. R. 141-085-0755 - Advance Mitigation
(1)
Set-Aside Excess Credits. As part of the existing, active individual
removal-fill permit application process, an applicant may request that the
Department consider that the proposed permittee-responsible CM (as documented
in a CM Plan prepared in accordance with OAR 141-085-0705) could produce
mitigation credits in excess of those needed to satisfy project
requirements.
(2) Additional
Information Required. If the applicant desires to preserve the option of
receiving additional mitigation credit from the excess credits for future
projects by the same applicant and by up to one additional party, then the
following additional information must be submitted as a part of the applicant's
CM plan:
(a) The specific area(s) of the CM
site that compensates for the specific permitted effect, and identification of
the specific areas of the CM site that are proposed for credit in future
projects;
(b) A table showing how
much credit, under suitable mitigation accounting in OAR 141-085-0692, is being
claimed at the CM site; and
(c) The
name of any additional person who would use the advance credits.
(3) Applicant Assumes All Risk. If
the applicant elects to pursue this option, he/she does so completely at
his/her own risk. CM in advance does not create the presumption that a proposed
future wetland impact will be authorized, or that the CM will be considered
suitable CM. A separate alternatives analysis will be required for each and
every separate individual removal-fill permit application.
(4) Monitoring Requirements. Monitoring to
determine if success criteria are met must continue for five years or until the
success criteria are achieved, whichever is longer. Such monitoring
requirements will apply to each designated mitigation area, or for the entire
mitigation site if constructed at one time.
(5) Conversion of Unused Credits. Unused
credits may be converted to mitigation bank credits at the discretion of the
Department and in accordance with OAR 141-085-0720 to OAR
141-085-0740.
Notes
Statutory/Other Authority: ORS 196.825 & ORS 196.600 - 196.692
Statutes/Other Implemented: ORS 196.600 - 196.692 & 196.800 - 196.990
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.