Or. Admin. R. 330-130-0050 - Procedures for Class 2 Buildings
(1) Role of the agency.
(a) The agency must notify the department of
Class 2 projects.
(b) The agency
shall determine that the design incorporates all reasonable cost-effective
ECMs. ECMs or ECM packages with a Simple Payback shorter than equipment life
shall be considered cost-effective for Class 2 Buildings. The agency, with
assistance from the design team as necessary, shall provide preliminary
benefit/cost results for each ECM implemented.
(c) The agency must send the list of energy
efficiency measures included in the building design to the
department.
(d) Upon completion of
construction, the agency must send a list of the measures that were actually
installed in the building to the department.
(2) Role of the department. The department
shall be available to the agency to advise or suggest potential energy saving
measures.
Notes
Stat. Auth.: ORS 276.900 - 276.915
Stats. Implemented: ORS 469
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.