Or. Admin. R. 330-130-0050 - Procedures for Class 2 Buildings

(1) Role of the agency.
(a) The agency must notify the department of Class 2 projects.
(b) The agency shall determine that the design incorporates all reasonable cost-effective ECMs. ECMs or ECM packages with a Simple Payback shorter than equipment life shall be considered cost-effective for Class 2 Buildings. The agency, with assistance from the design team as necessary, shall provide preliminary benefit/cost results for each ECM implemented.
(c) The agency must send the list of energy efficiency measures included in the building design to the department.
(d) Upon completion of construction, the agency must send a list of the measures that were actually installed in the building to the department.
(2) Role of the department. The department shall be available to the agency to advise or suggest potential energy saving measures.

Notes

Or. Admin. R. 330-130-0050
DOE 1-1990, f. & cert. ef. 4-2-90; DOE 1-1998, f. & cert. ef. 3-26-98; DOE 4-2001, f. 11-5-01, cert. ef. 11-15-01; DOE 1-2003, f. & cert. ef. 1-10-03; DOE 5-2008, f. 7-29-08, cert. ef. 8-1-08; DOE 5-2011, f. & cert. ef. 6-27-11; DOE 6-2017, f. & cert. ef. 8/15/2017

Stat. Auth.: ORS 276.900 - 276.915

Stats. Implemented: ORS 469