Or. Admin. R. 340-014-0120 - Criteria for Approval of a GEMS Achiever Permit
An agency or agencies may approve a GEMS Achiever Permit (also known as Tier II) upon demonstration to the agency's satisfaction that the applicant has:
(1) Implemented, and
will maintain and improve a robust environmental management system that is
certified as meeting the ISO 14001 standard, or meets the purpose or intent of
each of the ISO 14001 clauses, and supports verification; committed to
maintaining and exceeding regulatory compliance; committed to applying the
pollution prevention definition and pollution prevention hierarchy in setting
objectives and targets and developing the environmental program; and committed
to continual improvement;
(2)
Evaluated environmental impacts and set objectives and targets that will
achieve superior environmental performance for those site-based aspects that
have significant impacts, taking into consideration both regulated and
unregulated pollutants and other environmental impacts;
(3) Developed an environmental program that
will achieve environmental results that are significantly better than otherwise
required by law;
(4) Established
performance measures that will be used to explain environmental information in
context with past performance;
(5)
Submitted a baseline performance report that summarizes:
(a) Environmental policies affecting the
facility operations;
(b)
Environmental information regarding significant environmental impacts,
including those appropriate to the scope of the targeted impacts; and
(c) Performance measures and performance
achievements, including a description of the environmental program that will
achieve the results described in sections (2) and (3) above, and a
demonstration that the facility has reduced overall environmental impacts in
the three year period prior to applying for the GEMS Permit, or, for new
facilities, demonstrated by methods used to minimize environmental impacts in
the design of the facility; and
(6) Developed a plan for an annual update of
the performance report that updates the information required in (5) above, and
includes:
(a) Performance achievements, and,
if appropriate, a description of any obstacles encountered and how
addressed;
(b) Environmental
management system deficiencies and how addressed;
(c) Compliance issues, and how
addressed;
(d) Stakeholder
involvement activities, and input received from stakeholders and how addressed;
and
(e) Revised objectives and
targets for targeted impacts; and
(7) Developed a program for stakeholder
involvement appropriate to the scope of the environmental management system and
site-based impacts, and has implemented and continues to implement activities
that provide for dialogue regarding environmental performance and a mechanism
for receiving, considering and responding to comments received. The facility
shall:
(a) Encourage public inquiries and
comments regarding the facility's environmental performance;
(b) Provide mechanisms to discuss the
environmental policy, annual performance report, environmental aspects and
impacts, and establishment of objectives and targets; and
(c) Consider results of stakeholder
involvement in decision making, and respond to comments received.
Notes
Statutory/Other Authority: ORS 468.020
Statutes/Other Implemented: ORS 468.501, 468.503, 468.506, 468.508, 468.511, 468.513, 468.516, 468.518 & 468.521
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.