(1) Information Required. The owner or
operator of a source subject to Major NSR or State NSR must submit an
application and all information DEQ needs to perform any analysis or make any
determination required under this division and OAR 340 division 225. The
information must be in writing on forms supplied or approved by DEQ and include
the information required to apply for a permit or permit modification under:
(a) OAR 340 division 216 for Major NSR or
Type A State NSR action; or
(b) OAR
340 division 216 or 218, whichever is applicable, for Type B State NSR
actions.
(2) Application
Processing:
(a) For Type B State NSR, DEQ
will review applications and issue permits using the procedures in OAR 340
division 216 or 218, whichever is applicable.
(b) For Major NSR and Type A State NSR:
(A) Notwithstanding the requirements of OAR
340-216-0040(11), within 30 days after receiving an ACDP permit application to
construct, or any additional information or amendment to such application, DEQ
will advise the applicant whether the application is complete or if there is
any deficiency in the application or in the information submitted. For purposes
of this section, an application is complete as of the date on which DEQ
received all required information;
(B) Upon determining that an application is
complete, DEQ will undertake the public participation procedures in OAR 340
division 209 for a Category IV permit action; and
(C) DEQ will make a final determination on
the application within twelve months after receiving a complete
application.
(3) An owner or operator that obtained
approval of a project under this division must obtain approval for a revision
to the project according to the permit application requirements in this
division and OAR 340 division 216 or 218, whichever is applicable, prior to
initiating the revision. If construction has commenced, the owner or operator
must temporarily halt construction until a revised permit is issued. The
following are considered revisions to the project that would require approval:
(a) A change that would increase permitted
emissions;
(b) A change that would
require a re-evaluation of the approved control technology; or
(c) A change that would increase air quality
impacts.
(4) For major
NSR and Type A State NSR permit actions, an ACDP that approves construction
must require construction to commence within 18 months of issuance.
Construction approval terminates and is invalid if construction is not
commenced within 18 months after DEQ issues such approval, or by the deadline
approved by DEQ in an extension under section (5). Construction approval also
terminates and is invalid if construction is discontinued for a period of 18
months or more or if construction is not completed within 18 months of the
scheduled time. An ACDP may approve a phased construction project with separate
construction approval dates for each subsequent phase and, for purposes of
applying this section, the construction approval date for the second and
subsequent phases will be treated as the construction approval issuance
date.
(5) For major NSR and Type A
State NSR permit actions, DEQ may grant for good cause two 18-month
construction approval extensions as follows:
(a) Except as provided in subsection (i), for
the first extension, the owner or operator must submit an application to modify
the permit that includes the following:
(A) A
detailed explanation of why the source could not commence construction within
the initial 18-month period; and
(B) Payment of the simple technical permit
modification fee in OAR
340-216-8020 Part 3.
(b) Except as provided in subsection (i), for
the second extension, the owner or operator must submit an application to
modify the permit that includes the following for the original regulated
pollutants subject to Major NSR or Type A State NSR:
(A) A detailed explanation of why the source
could not commence construction within the second 18-month period;
(B) A review of the original LAER or BACT
analysis for potentially lower limits and a review of any new control
technologies that may have become commercially available since the original
LAER or BACT analysis;
(C) A review
of the air quality analysis to address any of the following:
(i) All ambient air quality standards and PSD
increments that were subject to review under the original
application;
(ii) Any new competing
sources or changes in ambient air quality since the original application was
submitted;
(iii) Any new ambient
air quality standards or PSD increments for the regulated pollutants that were
subject to review under the original application; and
(iv) Any changes to EPA approved models that
would affect modeling results since the original application was submitted,
and
(D) Payment of the
moderate technical permit modification fee plus the modeling review fee in OAR
340-216-8020 Part 4.
(c)
Except as provided in subsection (i), the permit will be terminated 54 months
after it was initially issued if construction does not commence during that 54
month period. If the owner or operator wants approval to construct beyond the
termination of the permit, the owner or operator must submit an application for
a new Major NSR or Type A State NSR permit.
(d) If construction is commenced prior to the
date that construction approval terminates, the permit can be renewed or the
owner or operator may apply for a Title V permit as required in OAR
340-218-0190;
(e) To request a
construction approval extension under subsection (a) or (b), the owner or
operator must submit an application to modify the permit at least 30 days but
not more than 90 days prior to the end of the current construction approval
period.
(f) Construction may not
commence during the period from the end of the preceding construction approval
to the time DEQ approves the next extension.
(g) DEQ will make a proposed permit
modification available using the following public participation procedures in
OAR 340 division 209:
(A) Category II for an
extension that does not require an air quality analysis; or
(B) Category III for an extension that
requires an air quality analysis.
(h) DEQ will grant a permit modification
extending the construction approval for 18 months from the end of the first or
second 18-month construction approval period, whichever is applicable, if:
(A) Based on the information required to be
submitted under subsection (a) or (b), DEQ determines that the proposed source
will continue to meet NSR requirements; and
(B) For any extension, the area impacted by
the source has not been redesignated to sustainment or nonattainment prior to
the granting of the extension.
(i) If the area where the source is located
is redesignated to sustainment or nonattainment before any extension is
approved, the owner or operator must demonstrate compliance with the
redesignated area requirements if the source is subject to Major or Type A
State NSR for the redesignated pollutant, and must obtain the appropriate
permit or permit revision before construction may commence. The new permit or
permit revision under this subsection will be considered to start a new initial
18-month construction approval period.
(6) Approval to construct does not relieve
any owner or operator of the responsibility to comply fully with applicable
provisions of the SIP and any other requirements under local, state or federal
law;
(7) Sources that are subject
to OAR 340 division 218, Oregon Title V Permits, are subject to the following:
(a) Except as prohibited in subsection (b),
approval to construct a source under an ACDP issued under OAR 340 division 216
authorizes construction and operation of the source, until the later of:
(A) One year from the date of initial startup
of operation of the source subject to Major NSR or Type A State NSR;
or
(B) If a timely and complete
application for an Oregon Title V Operating Permit is submitted, the date of
final action by DEQ on the Oregon Title V Operating Permit
application.
(b) Where
an existing Oregon Title V Operating Permit prohibits construction or a change
in operation, the owner or operator must obtain a Title V permit revision
before commencing the construction, continuing the construction or making the
change in operation.
NOTE: This rule is included in the State of Oregon Clean Air
Act Implementation Plan that EQC adopted under OAR 340-200-0040
Notes
Or. Admin. R.
340-224-0030
DEQ 25-1981, f. & ef.
9-8-81; DEQ 18-1984, f. & ef. 10-16-84; DEQ 13-1988, f. & cert. ef.
6-17-88; DEQ 4-1993, f. & cert. ef. 3-10-93; DEQ 12-1993, f. & cert.
ef. 9-24-93; Renumbered from 340-020-0230; DEQ 19-1993, f. & cert. ef.
11-4-93; DEQ 24-1994, f. &cert. ef. 10-28-94; DEQ 22-1995, f. &cert.
ef. 10-6-95; DEQ 26-1996, f. & cert. ef. 11-26-96; DEQ14-1999, f. &
cert. ef. 10-14-99, Renumbered from 340-028-1910; DEQ 6-2001, f. 6-18-01, cert.
ef. 7-1-01; DEQ 1-2004, f.& cert. ef. 4-14-04;
DEQ
7-2015, f. & cert. ef.
4/16/2015;
DEQ
9-2021, minor correction filed 07/01/2021, effective
7/1/2021
Statutory/Other Authority: ORS
468.020,
468A.025,
468A.035,
468A.040,
468A.050,
468A.055
& 468A.070
Statutes/Other Implemented: ORS
468A