Or. Admin. R. 340-242-0380 - When Will the Department Act on a Submitted Permit Application?
(1) The Department
will notify the applicant within 15 days of filing an application if further
information is needed or if the application is complete.
(2) The Department will grant or deny a
letter permit within 45 days of receiving a complete application.
NOTE: These rules are included in the State of Oregon Clean Air Act Implementation Plan as adopted by the Environmental Quality Commission under OAR 340-200-0040.
Notes
Stat. Auth.: ORS 468.020
Stats. Implemented: ORS 468A.363