Or. Admin. R. 340-242-0380 - When Will the Department Act on a Submitted Permit Application?

(1) The Department will notify the applicant within 15 days of filing an application if further information is needed or if the application is complete.
(2) The Department will grant or deny a letter permit within 45 days of receiving a complete application.

NOTE: These rules are included in the State of Oregon Clean Air Act Implementation Plan as adopted by the Environmental Quality Commission under OAR 340-200-0040.

Notes

Or. Admin. R. 340-242-0380
DEQ 17-1996, f. & cert. ef. 8-14-96; DEQ 14-1999, f. & cert. ef. 10-14-99, Renumbered from 340-030-1180

Stat. Auth.: ORS 468.020

Stats. Implemented: ORS 468A.363

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.