Or. Admin. R. 632-030-0041 - Permit and Exemption Transfer
Current through Register Vol. 61, No. 4, April 1, 2022
(1) An operating permit may be transferred as
provided in ORS 517.833, subject to the
following requirements:
(a) A person
requesting transfer must submit a completed application on a form prescribed by
the Department.
(b) The application
must be signed by the applicant, current permittee, landowner, and mineral
estate owner if different from the landowner.
(c) The applicant must submit the transfer
application fee as provided and not to exceed in ORS
517.800.
(d) The applicant must submit a bond or
alternative form of security acceptable to the Department.
(2) Prior to approving a permit transfer, the
Department may review the existing operating permit and reclamation plan and
the transfer of the permit may be denied or conditioned based on the failure of
existing operations to comply with the permit, plan, provisions of the Mined
Land Reclamation Act, or these rules. In addition, the Department may review
existing operations to determine whether an amendment to operating permit or
reclamation plan is appropriate under ORS
517.831 or
517.835.
(3) A limited exemption may be transferred
subject to the following requirements:
(a) A
person requesting transfer must submit a completed application on a form
prescribed by the Department.
(b)
The application must be signed by the applicant, current exemption holder,
landowner, and mineral estate owner if different from the landowner.
(c) The applicant must submit the transfer
application processing charge not to exceed $250.
Notes
Stat. Auth.: ORS 516.090, 517.810, 517.833 & 517.840