Or. Admin. R. 660-023-0040 - ESEE Decision Process
(1)
Local governments shall develop a program to achieve Goal 5 for all significant
resource sites based on an analysis of the economic, social, environmental, and
energy (ESEE) consequences that could result from a decision to allow, limit,
or prohibit a conflicting use. This rule describes four steps to be followed in
conducting an ESEE analysis, as set out in detail in sections (2) through (5)
of this rule. Local governments are not required to follow these steps
sequentially, and some steps anticipate a return to a previous step. However,
findings shall demonstrate that requirements under each of the steps have been
met, regardless of the sequence followed by the local government. The ESEE
analysis need not be lengthy or complex, but should enable reviewers to gain a
clear understanding of the conflicts and the consequences to be expected. The
steps in the standard ESEE process are as follows:
(a) Identify conflicting uses;
(b) Determine the impact area;
(c) Analyze the ESEE consequences;
and
(d) Develop a program to
achieve Goal 5.
(2)
Identify conflicting uses. Local governments shall identify conflicting uses
that exist, or could occur, with regard to significant Goal 5 resource sites.
To identify these uses, local governments shall examine land uses allowed
outright or conditionally within the zones applied to the resource site and in
its impact area. Local governments are not required to consider allowed uses
that would be unlikely to occur in the impact area because existing permanent
uses occupy the site. The following shall also apply in the identification of
conflicting uses:
(a) If no uses conflict
with a significant resource site, acknowledged policies and land use
regulations may be considered sufficient to protect the resource site. The
determination that there are no conflicting uses must be based on the
applicable zoning rather than ownership of the site. (Therefore, public
ownership of a site does not by itself support a conclusion that there are no
conflicting uses.)
(b) A local
government may determine that one or more significant Goal 5 resource sites are
conflicting uses with another significant resource site. The local government
shall determine the level of protection for each significant site using the
ESEE process and/or the requirements in OAR 660-023-0090 through 660-023-0230
(see OAR 660-023-0020(1)).
(3) Determine the impact area. Local
governments shall determine an impact area for each significant resource site.
The impact area shall be drawn to include only the area in which allowed uses
could adversely affect the identified resource. The impact area defines the
geographic limits within which to conduct an ESEE analysis for the identified
significant resource site.
(4)
Analyze the ESEE consequences. Local governments shall analyze the ESEE
consequences that could result from decisions to allow, limit, or prohibit a
conflicting use. The analysis may address each of the identified conflicting
uses, or it may address a group of similar conflicting uses. A local government
may conduct a single analysis for two or more resource sites that are within
the same area or that are similarly situated and subject to the same zoning.
The local government may establish a matrix of commonly occurring conflicting
uses and apply the matrix to particular resource sites in order to facilitate
the analysis. A local government may conduct a single analysis for a site
containing more than one significant Goal 5 resource. The ESEE analysis must
consider any applicable statewide goal or acknowledged plan requirements,
including the requirements of Goal 5. The analyses of the ESEE consequences
shall be adopted either as part of the plan or as a land use
regulation.
(5) Develop a program
to achieve Goal 5. Local governments shall determine whether to allow, limit,
or prohibit identified conflicting uses for significant resource sites. This
decision shall be based upon and supported by the ESEE analysis. A decision to
prohibit or limit conflicting uses protects a resource site. A decision to
allow some or all conflicting uses for a particular site may also be consistent
with Goal 5, provided it is supported by the ESEE analysis. One of the
following determi-nations shall be reached with regard to conflicting uses for
a significant resource site:
(a) A local
government may decide that a significant resource site is of such importance
compared to the conflicting uses, and the ESEE consequences of allowing the
conflicting uses are so detrimental to the resource, that the conflicting uses
should be prohibited.
(b) A local
government may decide that both the resource site and the conflicting uses are
important compared to each other, and, based on the ESEE analysis, the
conflicting uses should be allowed in a limited way that protects the resource
site to a desired extent.
(c) A
local government may decide that the conflicting use should be allowed fully,
notwithstanding the possible impacts on the resource site. The ESEE analysis
must demon-strate that the conflicting use is of sufficient importance relative
to the resource site, and must indicate why measures to protect the resource to
some extent should not be provided, as per subsection (b) of this
section.
Notes
Stat. Auth.: ORS 183 & ORS 197
Stats. Implemented: ORS 197.040 & ORS 197.225 - ORS 197.245
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.