Or. Admin. R. 860-021-0057 - Connection of Residential Energy Utility Service
(1) This rule applies to the connection of
energy service for an applicant or customer who has satisfied the requirements
of all applicable rules and regulations, and requested connection. This rule
applies for connection at a location with existing service facilities where the
utility need only activate service, or after any necessary line extension,
construction or repair work has been completed.
(2) Each energy utility must provide a means
by which an applicant or customer may contact the utility on a Business Day so
that the applicant or customer may pay applicable charges, submit any necessary
credit information and request connection of service. For purposes of this
rule, Business Day is defined as Monday through Friday, 8:00 a.m. to 5:00 p.m.,
excluding state- or utility-recognized holidays.
(3) An energy utility must connect service as
soon as reasonably possible, within the normal course of business, after an
applicant or customer has satisfied the requirements for and requested
connection. At a minimum, service must be connected within two Business Days,
except as provided in section (4) of this rule.
(4) This section only applies to a natural
gas service connection that is completed between September 15 and November 15
of each year, at an address where the applicant received service at any time
during the past 12 months that was disconnected, but not reconnected within 20
days. Service must be connected as soon as reasonably possible, within the
normal course of business, after an applicant or customer has satisfied the
requirements for and requested connection. At a minimum:
(a) Service must be connected within two (2)
Business Days when the applicant's prior service at the address was
disconnected from August 15 to November 15 of the current year.
(b) Service must be connected within five (5)
Business Days when the applicant's prior service at the address was
disconnected from November 16 of the previous year to August 14 of the current
year.
(5) With
Commission concurrence, the connection requirements under this rule may be
temporarily waived for any cause not reasonably within the control of the
utility including, but not limited to, the following:
(a) A documented Force Majeure
event;
(b) An action or default by
an applicant or other person outside of the utility's control, including a
cancellation of the request made by the applicant or customer;
(c) Major events, such as storms or system
outages;
(d) Safety-related issues
that preclude the utility from connecting service;
(e) The applicant's facilities cannot be
accessed due to circumstances beyond the utility's control;
(f) The utility's equipment or facilities
prevent the reconnection from occurring; or
(g) When the Commission approves a
waiver.
Notes