Or. Admin. R. 860-022-0017 - Announcement of Utility Tariff Changes
(1) Within 15 days of filing with the
Commission new or revised tariff schedules which constitute a general rate
revision, an energy or large telecommunications utility shall inform its
customers of the filing. A "general rate revision" is a filing by an energy or
large telecommunications utility which affects all or most of a utility's rate
schedules. "General rate revision" excludes changes in an automatic adjustment
clause under ORS 757.210(1),
changes in the credit reflected on certain electric company rate schedules
relating to Section 5(c) of the Pacific Northwest Electric Power Planning and
Conservation Act of 1980, or similar changes in one rate schedule, such as for
an amortization, that affects other rate schedules.
(2) The energy or large telecommunications
utility shall inform its customers by:
(a)
Inserting a display announcement, not less than a three column standard
advertising unit (SAU) by ten-inch advertisement, at least once in a newspaper
of general circulation in the communities served by the energy or large
telecommunications utility;
(b)
Inserting an announcement in the energy or large telecommunications utility's
regular billing to its customers; or
(c) Mailing an announcement to each
customer.
(3) The energy
or large telecommunications utility's announcement shall include:
(a) The approximate annualized amount of the
proposed total change, expressed both in dollar and in percentage terms; and
the approximate amount of the proposed change for an average residential
customer's monthly bill, expressed in dollar terms;
(b) A brief statement of the reasons why the
energy or large telecommunications utility seeks the change;
(c) A statement that copies of the energy or
large telecommunications utility's testimony and exhibits are available for
inspection at its main and district offices;
(d) The mailing address and telephone number
of the energy or large telecommunications utility's office that customers may
contact for additional information about the filing;
(e) The mailing address and toll-free
telephone number of the Commission to which requests to receive notice of the
time and place of any hearing on the matter may be directed; and
(f) A statement that the purpose of the
announcement is to provide the energy or large telecommunications utility's
customers with general information about the utility's proposals and their
effects on its customers, but that the calculations and statements contained in
the announcement are not binding on the Commission.
(4) Within 20 days of issuing the
announcement, the energy or large telecommunications utility shall file an
affidavit that notice has been given and a copy of the notice.
(5) An energy or large telecommunications
utility may submit to the Commission, and request approval of, a list of the
newspapers of general circulation in the communities served by the utility. The
utility may revise the list by written request to the Commission.
(6) The Commission may waive the requirements
of this rule upon a showing by the energy or large telecommunications utility
that the notice required by this rule has been given with respect to a
particular general rate revision, and upon a further showing that additional
notice with respect to that rate revision would be duplicative, confusing to
customers, and burdensome to the utility.
Notes
Stat. Auth.: ORS 183, 756, 757 & 759
Stats. Implemented: ORS 757.205 - 757.220 & 759.175 - 759.190