Or. Admin. R. 860-038-0750 - De-Enrollment Due to Failure to Meet Load Standard
If the actual load of a facility served under the New Large Load Direct Access Program fails to meet the requirements outlined in OAR 860-038-0730(3) and the electric company elects to de-enroll the participant, the electric company must provide written notification to the New Large Load participant and the Commission of its proposal to move the participant to the appropriate cost-of-service rate schedule.
Notes
Statutory/Other Authority: ORS Ch. 183, 756, 757
Statutes/Other Implemented: ORS 756.040, 757.600 through 757.667