Or. Admin. R. 860-084-0210 - Capacity Reservation, Timing, and Duration

(1) A capacity reservation expires if a completed interconnection application is not filed within two months of the reservation start date or if the system has not been installed within twelve months of the reservation start date, unless a waiver is granted under OAR 860-084-0000. Any delay resulting from the utility not completing required work to connect the eligible system to the grid will be excluded from this 12-month installation requirement.
(2) Once the capacity reservation expires, the retail electricity consumer must newly apply for a capacity reservation and will not be given preferential treatment.

Notes

Or. Admin. R. 860-084-0210
PUC 2-2010, f. & cert. ef. 6-1-10; PUC 7-2011, f. & cert. ef. 9-30-11

Stat Auth: ORS 757.360 - 757.380

Stats. Implemented: ORS 757.360 - 757.380

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.