Or. Admin. R. 860-084-0280 - Interconnection Cost Responsibility
(1) For a Level 1 interconnection review, the
electric company may not charge an application, or other fee, unless otherwise
directed by the Commission. However, if an application for Level 1
interconnection review is denied because it does not meet the requirements for
Level 1 interconnection review and the applicant resubmits the application
under another review procedure, the electric company may impose a fee for the
resubmitted application.
(2) For a
Level 2 interconnection review, the electric company may charge fees of up to
$50.00 plus $1.00 per kilowatt of the qualifying system's capacity, plus the
reasonable cost of any required minor modifications to the electric
distribution system or additional review. Costs for such minor modifications or
additional review will be based on the electric company's non-binding, good
faith estimates and the ultimate actual installed costs. Costs for engineering
work done as part of any additional review will not exceed $100.00 per hour. An
electric company may adjust the $100.00 hourly rate once in January of each
year to account for inflation and deflation as measured by the Consumer Price
Index.
(3) For a Level 3
interconnection review, the electric company may charge fees of up to $100.00
plus $2.00 per kilowatt of the qualifying system's capacity, as well as charges
for actual time spent on any required impact or facilities studies. Costs for
engineering work done as part of an impact study or interconnection facilities
study will not exceed $100.00 per hour. An electric company may adjust the
$100.00 hourly rate once in January of each year to account for inflation and
deflation as measured by the Consumer Price Index. If the electric company must
install facilities in order to accommodate the interconnection of the
qualifying system, the cost of such facilities will be the responsibility of
the applicant.
(4) Interconnected
net metered systems must be equipped with two meters: metering equipment that
can measure the flow of electricity in both directions (complying with ANSI
C12.1 standards and OAR 860-023-0015) to replace the existing customer meter,
and a second meter that can measure the total output of the qualifying system.
Interconnected stand-alone systems using the bidding process must be equipped
with metering equipment that can measure the flow of electricity in both
directions (complying with ANSI C12.1 standards and OAR 860-023-0015). The
electric company will install the required metering equipment at the electric
company's expense for both the net metered and stand-alone system.
(a) The electric company constructs, owns,
operates, and maintains all meters and applicable interconnection facilities on
the company side of the retail electric consumer's meter, including, the second
meter installed to measure the total output of the qualifying system.
(b) The electric company must charge an
additional monthly service charge to the retail electricity customer for the
additional meter used to measure the total output of the qualifying system, as
established by Commission order.
(5) An eligible participant who is
reinstalling a contracted system and is eligible to continue in the solar
photovoltaic pilot program under an existing standard contract must pay the
expense of interconnection facilities, required additions or modifications to
the electric distribution system, interconnection review, or system upgrades in
the new location as applicable.
Notes
Stat Auth: ORS 757.360 - 757.380
Stats. Implemented: ORS 757.360 - 757.380
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.