Or. Admin. R. 860-084-0310 - Level 1 System Interconnection Review
(1) An eligible system is eligible for Level
1 interconnection review if:
(a) The facility
is inverter-based; and
(b) The
facility has a capacity of 25 kilowatts or less.
(2) The electric company must approve
interconnection under the Level 1 interconnection review procedure if:
(a) The aggregate generation capacity on the
distribution circuit to which the eligible system will interconnect, including
the capacity of the eligible system, may not contribute more than 10 percent to
the distribution circuit's maximum fault current at the point on the high
voltage (primary) level that is nearest the proposed point of common
coupling;
(b) An eligible system's
point of common coupling may not be on a transmission line, a spot network, or
an area network;
(c) If an eligible
system is to be connected to a radial distribution circuit, the aggregate
generation capacity connected to the circuit, including that of the eligible
system, may not exceed 15 percent of the circuit's total annual peak load, as
most recently measured at the substation;
(d) If an eligible system is to be connected
to a single-phase shared secondary, the aggregate generation capacity connected
to the shared secondary, including the eligible system, may not exceed 20
kilovolt-amps; and
(e) If a
single-phase eligible system is to be connected to a transformer center tap
neutral of a 240 volt service, the addition of the eligible system may not
create a current imbalance between the two sides of the 240 volt service of
more than 20 percent of nameplate rating of the service transformer.
(3) Within 10 business days after
the electric company notifies a Level 1 applicant that the application is
complete, the electric company must notify the applicant that:
(a) The eligible system meets all applicable
criteria and the interconnection is approved upon installation of any required
meter upgrade, completion of any required inspection of the facility, and
execution of an interconnection agreement; or
(b) The eligible system has failed to meet
one or more of the applicable criteria and the interconnection application is
denied.
(4) If an
electric company does not notify a Level 1 applicant in writing or by
electronic mail whether the interconnection is approved or denied within 20
business days after the receipt of an application, the interconnection will be
deemed approved. Interconnections approved under this section remain subject to
section (7) of this rule.
(5)
Within three business days after sending the notice to an applicant that the
proposed interconnection meets the Level 1 requirements, an electric company
must notify the applicant:
(a) Whether an
inspection of the eligible system for compliance with these interconnection
rules is required prior to the operation of the system; and
(b) That an interconnection agreement is
required for the eligible system. The electric company must also execute and
send to the applicant a Level 1 interconnection agreement, unless the applicant
has already submitted such an agreement with its application for
interconnection.
(6) On
receipt of an executed interconnection agreement from the applicant and
satisfactory completion of any required inspection, the electric company must
approve the interconnection, conditioned on compliance with all applicable
building codes.
(7) The retail
electric customer must notify the electric company of the anticipated start
date for operation of the eligible system at least five business days prior to
starting operation, either through the submittal of the interconnection
agreement or in a separate notice. If the electric company requires an
inspection of the eligible system, the applicant may not begin operating the
facility until satisfactory completion of the inspection.
(8) If an application for Level 1
interconnection review is denied because it does not meet one or more of the
applicable requirements in this rule, an applicant may resubmit the application
under the Level 2 or Level 3 interconnection review procedure, as
appropriate.
Notes
Stat Auth: ORS 757.360 - 757.380
Stats. Implemented: ORS 757.360 - 757.380
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.