Or. Admin. R. 860-084-0320 - Level 2 System Interconnection Review
(1) An electric company must apply the
following Level 2 interconnection review procedure for an application to
interconnect an eligible system that meets the following criteria:
(a) The facility has a capacity of 500
kilowatts or less; and
(b) The
facility does not qualify for or failed to meet applicable Level 1
interconnection review procedures.
(2) The electric company must approve
interconnection under the Level 2 interconnection review procedure if:
(a) The aggregate generation capacity on the
distribution circuit to which the eligible system will interconnect, including
the capacity of the eligible system, will not cause any distribution protective
equipment (including, but not limited to, substation breakers, fuse cutouts,
and line reclosers), or customer equipment on the electric distribution system,
to exceed 90 percent of the short circuit interrupting capability of the
equipment. In addition, an eligible system may not be connected to a circuit
that already exceeds 90 percent of the short circuit interrupting capability,
prior to interconnection of the facility;
(b) If there are posted transient stability
limits to generating units located in the general electrical vicinity of the
proposed point of common coupling, including, but not limited to within three
or four transmission voltage level busses, the aggregate generation capacity,
including the eligible system, connected to the distribution low voltage side
of the substation transformer feeding the distribution circuit containing the
point of common coupling may not exceed 10 megawatts;
(c) The aggregate generation capacity
connected to the distribution circuit, including the eligible system, may not
contribute more than 10 percent to the distribution circuit's maximum fault
current at the point on the high voltage (primary) level nearest the proposed
point of common coupling;
(d) If an
eligible system is to be connected to a radial distribution circuit, the
aggregate generation capacity connected to the electric distribution system by
non-electric company sources, including the eligible system, may not exceed 15
percent of the total circuit annual peak load. For the purposes of this
subsection, annual peak load will be based on measurements taken over the 12
months previous to the submittal of the application, measured for the circuit
at the substation nearest to the eligible system;
(e) If an eligible system is to be connected
to three-phase, three wire primary electric company distribution lines, a
three-phase or single-phase generator must be connected
phase-to-phase;
(f) If an eligible
system is to be connected to three-phase, four wire primary electric company
distribution lines, a three-phase or single-phase generator must be connected
line-to-neutral and must be effectively grounded;
(g) If an eligible system is to be connected
to a single-phase shared secondary, the aggregate generation capacity on the
shared secondary, including the eligible system, may not exceed 20
kilovolt-amps;
(h) If an eligible
system is single-phase and is to be connected to a transformer center tap
neutral of a 240 volt service, the addition of the eligible system may not
create a current imbalance between the two sides of the 240 volt service that
is greater than 20 percent of the nameplate rating of the service
transformer;
(i) An eligible
system's point of common coupling may not be on a transmission line;
and
(j) If an eligible system's
proposed point of common coupling is on a spot or area network, the
interconnection must meet the following additional requirements:
(A) For an eligible system that will be
connected to a spot network circuit, the aggregate generation capacity
connected to that spot network from the eligible system, and any generating
facilities, may not exceed five percent of the spot network's maximum
load;
(B) For an eligible system
that utilizes inverter-based protective functions, which will be connected to
an area network, the eligible system, combined with any other generating
facilities on the load side of network protective devices, may not exceed 10
percent of the minimum annual load on the network, or 500 kilowatts, whichever
is less. The percent of minimum load must be calculated based on the minimum
load occurring during an off-peak daylight period; and
(C) For an eligible system that will be
connected to a spot or an area network that does not utilize inverter-based
protective functions, or for an inverter-based eligible system that does not
meet the requirements of paragraphs (A) or (B) of this subsection, the eligible
system must utilize low forward power relays or other protection devices that
ensure no export of power from the eligible system, including inadvertent
export (under fault conditions) that could adversely affect protective devices
on the network.
(3) Within 15 business days after notifying a
Level 2 applicant that the application is complete, the electric company must
perform an initial review of the proposed interconnection to determine whether
the interconnection meets the applicable criteria. During this initial review,
the electric company may, at its own expense, conduct any studies or tests it
deems necessary to evaluate the proposed interconnection and provide notice to
the applicant of one of the following determinations:
(a) The eligible system meets the applicable
requirements and that interconnection will be approved following any required
inspection of the facility and fully executed interconnection agreement. Within
three business days after this notice, the electric company must provide the
applicant with an executable interconnection agreement;
(b) The eligible system failed to meet one or
more of the applicable requirements, but the electric company determined that
the eligible system may be interconnected consistent with safety, reliability,
and power quality. In this case, the electric company must notify the applicant
that the interconnection will be approved following any required inspection of
the facility and fully executed interconnection agreement. Within five business
days after this notice, the electric company must provide the applicant with an
executable interconnection agreement; or
(c) The eligible system failed to meet one or
more of the applicable requirements, and that additional review would not
enable the electric company to determine that the eligible system could be
interconnected consistent with safety, reliability, and power quality. In such
a case, the electric company must notify the applicant that the interconnection
application has been denied and must provide an explanation of the reason(s)
for the denial, including a list of additional information, or modifications to
the eligible system, or both, which would be required in order to obtain an
approval under Level 2 interconnection procedures.
(4) An applicant that receives an
interconnection agreement under subsection (3)(a) or (3)(b) of this rule must:
(a) Execute the agreement and return it to
the electric company at least 10 business days prior to starting operation of
the eligible system (unless the electric company does not so require);
and
(b) Indicate to the electric
company the anticipated start date for operation of the eligible
system.
(5) The electric
company may require an electric company inspection of an eligible system for
compliance with these solar photovoltaic rules prior to operation, and may
require and arrange for witness of commissioning tests as set forth in IEEE
standards. The electric company must schedule any inspections or tests under
this section promptly and within a reasonable time after submittal of the
application. The applicant may not begin operating the eligible system until
after the inspection and testing is completed.
(6) Approval of interconnected operation of
any Level 2 eligible system must be conditioned on all of the following
occurring:
(a) Approval of the interconnection
by the electrical code official with jurisdiction over the
interconnection;
(b) Successful
completion of any electric company inspection or witnessing of commissioning
tests, or both, requested by the electric company; and
(c) Passing of the planned start date
provided by the applicant.
(7) If an application for Level 2
interconnection review is denied because it does not meet one or more of the
requirements of this rule, the applicant may resubmit the application under the
Level 3 interconnection review procedure.
Notes
Stat Auth: ORS 757.360 - 757.380
Stats. Implemented: ORS 757.360 - 757.380
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.