Or. Admin. R. 860-084-0330 - Level 3 System Interconnection Review
(1) The electric company must apply the Level
3 review procedure for an application to interconnect an eligible system that
meets the following criteria:
(a) The
facility has a capacity of 500 kilowatts or less; and
(b) The facility does not qualify or failed
to meet Level 2 interconnection review procedures.
(2) Following receipt of a Level 3
application and within three business days of a request from the applicant, the
electric company must provide pertinent information to the applicant, such as
the available fault current at the proposed interconnection location, the
existing peak loading on the lines in the general vicinity of the eligible
system, and the configuration of the distribution lines at the proposed point
of common coupling.
(3) Within
seven business days after receiving a complete application for Level 3
interconnection review, the electric company must conduct an impact study which
will include a non-binding, good faith cost estimate. The impact study must be
conducted in accordance with good utility practice and must:
(a) Detail the impacts to the electric
distribution system that would result if the eligible system were
interconnected without modifications to either the eligible system or to the
electric distribution system;
(b)
Identify any modifications to the electric company's electric distribution
system that would be necessary to accommodate the proposed interconnection;
and
(c) Focus on power flows and
utility protective devices, including control requirements; and
(d) Include the following elements, as
applicable:
(A) A load flow study;
(B) A short-circuit study;
(C) A circuit protection and coordination
study;
(D) The impact on the
operation of the electric distribution system;
(E) A stability study, along with the
conditions that would justify including this element in the impact
study;
(F) A voltage collapse
study, along with the conditions that would justify including this element in
the impact study.
(4) The electric company must complete the
impact study and must notify the applicant within 30 calendar days of one of
the following results:
(a) Only minor
modifications to the electric company's electric distribution system are
necessary to accommodate interconnection. In such a case, the electric company
will send the applicant an interconnection agreement that details the scope of
the necessary modifications and a non-binding, good faith estimate of its cost;
or
(b) Substantial modifications to
the electric company's electric distribution system are necessary to
accommodate the proposed interconnection. In such a case, the electric company
must provide a non-binding, good faith estimate of the cost of the
modifications, which must be accurate to within plus or minus 25 percent. In
addition, the electric company must offer to conduct, at the applicant's
expense, an interconnection facilities study that must identify the types and
cost of equipment needed to safely interconnect the applicant's eligible
system.
(5) If the
proposed interconnection may affect electric transmission or delivery systems
other than those controlled by the electric company, operators of those other
systems may require additional studies to determine the potential impact of the
interconnection on those systems. If such additional studies are required, the
electric company must coordinate the studies but is not responsible for their
timing.
(6) If an applicant
requests a facilities study under subsection (4)(b), the electric company must
provide an interconnection facilities study agreement. The interconnection
facilities study agreement must describe the work to be undertaken in the
interconnection facilities study and must include a non-binding, good faith
estimate of the cost to the applicant for completion of the study. Upon the
execution by the applicant of the interconnection facilities study agreement,
the electric company will conduct an interconnection facilities study to
identify the facilities necessary to safely interconnect the eligible system
with the electric company's electric distribution system, and to propose a
non-binding, good faith estimate of the cost of those facilities and the time
required to build and install those facilities.
(7) Upon completion of an interconnection
facilities study, the electric company must provide the applicant with the
results of the study and an executable interconnection agreement. The agreement
must list the conditions and facilities necessary for the eligible system to
safely interconnect with the electric company's electric distribution system,
and must include a non-binding, good faith estimate of the cost of those
facilities and the estimated time required to build and install those
facilities.
(8) If the applicant
wishes to interconnect, it must execute the interconnection agreement and
return it to the electric company at least 10 business days prior to starting
operation of the eligible system (unless the electric company does not so
require), pay a deposit of not more than 50 percent of the estimated cost of
the facilities identified in the interconnection facilities study, complete
installation of the eligible system, and agree to pay the public utility the
actual installed cost of the facilities needed to interconnect as identified in
the interconnection facilities study.
(9) Within 15 business days after notice from
the applicant that the eligible system has been installed, the electric company
must inspect the eligible system and must arrange to witness any commissioning
tests required under IEEE standards. The electric company and the applicant
must select a date by mutual agreement for the electric company to witness
commissioning tests.
(10) If the
eligible system satisfactorily passes required commissioning tests, if any, the
electric company must notify the applicant in writing, within three business
days after the tests, of one of the following:
(a) The interconnection is approved and the
eligible system may begin operation; or
(b) The interconnection facilities study
identified necessary construction that has not been completed, the date upon
which the construction must be completed, and the date when the eligible system
may begin operation.
(11)
If the commissioning tests are not satisfactory, the applicant must repair or
replace the unsatisfactory equipment to reschedule a commissioning
test.
Notes
Stat Auth: ORS 757.360 - 757.380
Stats. Implemented: ORS 757.360 - 757.380
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.