Or. Admin. R. 918-305-0420 - Electrified Fixed Guideway Passenger Railway System Permits

(1) The signature of a general supervising electrician or limited supervising electrician shall be required on each permit to aid inspections by the division and indicate responsibility under ORS 479.950.
(2) A permit is required prior to start of any electrical work. Expansion of work under a permit may be added to an existing permit prior to final inspection.
(3) A permit must be posted in a conspicuous place near the main electrical panel location. If there is no main panel installed, the permit shall be posted in a conspicuous place on the job site.
(4) An electrical permit issued to one person or firm is not transferable and shall not permit any other person or firm to perform any electrical work thereunder.
(5) Any permittee holding an unexpired permit may apply for an extension of the time within which work may be completed.
(6) Permit fees shall be charged at $69 per hour including travel and office time with a minimum charge of one hour for any and all inspections performed on that permit.

Notes

Or. Admin. R. 918-305-0420
BCD 7-2000, f. 3-15-00, cert. ef. 4-1-00

Stat. Auth.: ORS 479.950

Stats. Implemented: ORS 479.950