Or. Admin. R. 918-308-0060 - Review and Approval Process
(1)
The division shall, after review of the application, submit the application to
the board for comments and recommendations, and grant or deny the application,
or seek clarification or corrections. If additional information or technical
corrections are necessary, comments may be provided and the municipality may be
allowed to submit changes.
(2) If a
complete and acceptable plan is not on file by January 1, the request for
delegation shall be denied for that year. An extension may be granted if agreed
to by the municipality, division, and county involved, if the municipality is a
city.
(3) If a municipality whose
authority was previously revoked reapplies for delegation of the electrical
program, it shall, in addition to its application, show how past deficiencies
were corrected and how they will be prevented in the future.
(4) A new delegation of authority shall be
provisional for a year. A municipality receiving a provisional delegation shall
amend its application, if necessary, to reflect desired changes. If no
amendments are filed by January 1, the prior application shall be used. The
division shall make site visitations as necessary to inform itself of how the
electrical program is being administered and how the operating plan is being
followed and file its report with the application. Once the application is
renewed no new applications are necessary unless the delegation is revoked or
yielded by the municipality.