Or. Admin. R. 918-309-0410 - Renewable Electrical Energy Permit Application
(1) A separate Renewable Electrical Energy
Permit Application Form and Renewable Electrical Energy Installer Log are to be
used for renewable energy electrical system installations. The Renewable
Electrical Energy Permit:
(a) Covers the
renewable electrical energy system installation and the alternating current
feeder connection to the structure where applicable. The permit shall include
an installer log to document all work performed under the permit; and
(b) May be purchased by a general contractor,
subcontractor, limited renewable energy contractor or property owner provided
the requirements of this rule are met.
(2) The renewable electrical energy
activities covered by the permit shall be declared at the time the permit is
purchased. New permits must be purchased for all other renewable electrical
energy installations;
(3) The
person applying for the permit shall:
(a)
Assume responsibility to call for an inspection after the permits are signed
by; the limited renewable energy contractor, signing supervisor or property
owner and that these installations are completed and comply with the
requirements of the renewable electrical energy laws and these rules;
(b) Be responsible for all corrections
required by the inspec-tor under the permit, regardless of who performs the
work; and
(c) Call for a final
inspection when needed corrections are made and the work is
completed.
(4) The
person obtaining the permit may:
(a) Include
any and all renewable electrical energy installations including those done by
separate installers, but the installations must be ready for inspection at the
first call for inspection. When this is done, the permit shall be completed and
separately signed by the person, also identifying the business responsible for
each type of renewable electrical energy installation.
(b) Receive up to two inspections. For
inspections in excess of those allowed under this rule, a charge of $86 per
hour including travel time and office time with a minimum charge of one hour
for each additional inspection shall be paid in advance.
(5) All parties performing work under the
permit shall be identifed at the time of permit is issued. If the party
performing the work is changed, the party who completed the work must be
identified.
(6) Nothwithstanding
the activities identified in the permit application, the permit only covers
those electrical installations that are in place at the time of the first call
for inspection of the renewable electrical energy work. A separate permit shall
be purchased for all other renewable electrical energy installations whether
the installations become ready for inspection at a later date or are done at a
later date.
(7) The Renewable
Electrical Energy InstallersLog shall be posted at the job site for signing by
appropriate persons installing the separate electrical systems as shown on the
form. The jurisdiction may require more than one installer log to be completed
and left at the job site.
Notes
Stat. Auth.: ORS 479.870
Stats. Implemented: ORS 479.870
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.