Or. Admin. Code § 345-027-0030 - Amendment to Extend Construction Beginning and Completion Deadlines
(1) The certificate
holder may request an amendment to extend the deadlines for beginning or
completing construction of the facility that the Council has specified in a
site certificate or an amended site certificate. The certificate holder shall
submit a request that includes an explanation of the need for an extension and
that conforms to the requirements of
345-027-0060 no later than six
months before the date of the applicable deadline, or, if the certificate
holder demonstrates good cause for the delay in submitting the request, no
later than the applicable deadline.
(2) A request within the time allowed in
section (1) to extend the deadlines for beginning or completing construction
suspends those deadlines until the Council acts on the request.
(3) The Council shall review the request for
amendment as described in OAR
345-027-0070.
(4) If the Council grants an amendment under
this rule, the Council shall specify new deadlines for beginning or completing
construction that are not more than two years from the deadlines in effect
before the Council grants the amendment.
(5) To grant an amendment extending the
deadline for beginning or completing construction of an energy facility subject
to OAR 345 024 0550, 345 024 0590, or 345 024 0620, the Council must find that
the facility complies with the carbon dioxide standard in effect at the time of
the Council's order on the amendment.
Notes
Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.370, 469.405 & 469.503