Or. Admin. Code § 345-027-0220 - Request for Approval
(1) Before
submitting a request for approval to construct, operate and retire a gas
storage testing pipeline, the certificate holder must:
(a) Inform the Department of the proposed
pipeline, including its diameter, length, location, capacity and maximum
operating pressure; and
(b) Provide
to the Department a map showing the location of the proposed
pipeline.
(2) After
receiving the information described in section (1) of this rule, the Department
must confer with the certificate holder about the Council substantive standards
and information requirements that might apply to the proposed pipeline and any
extraordinary circumstances that might affect the time requirements for
completing the approval process. Within 7 days after conferring with the
certificate holder, the Department must send a letter to the certificate holder
that includes the following:
(a)
Identification of the Council substantive standards that are applicable to the
request for approval of the proposed pipeline;
(b) Identification of the information
requirements that are applicable to the request for approval of the proposed
pipeline;
(c) The time requirements
for the approval process, if different from the time requirements described in
OAR 345-027-0530.
(3) The
certificate holder must submit to the Department a written request for approval
to construct, operate and retire a gas storage testing pipeline with the fee
required by the fee schedule established under ORS
469.441. The certificate holder
must submit two printed copies of the request, and an electronic version of the
full request in a non-copy-protected electronic format acceptable to the
Department. The certificate holder must provide additional printed copies to
the Department upon request and copies or access to copies to any person
requesting copies.
(4) In a request
for approval, the certificate holder must include:
(a) The name and mailing address of the
certificate holder and the name, mailing address, email address and phone
number of the individual responsible for submitting the request;
(b) A description of the purpose and
operation of the proposed pipeline and a discussion of whether the use of the
gas storage testing pipeline for reservoir testing or maintenance will require
an increase in the compression available in the Council certified facility to
which the proposed pipeline would connect in addition to the compression that
is permitted under the site certificate;
(c) Identification of the Council certified
facility to which the proposed pipeline would connect;
(d) A description of the proposed pipeline,
including its diameter, length, location, capacity and maximum operating
pressure;
(e) A map showing the
location of the proposed pipeline;
(f) A list of the names and mailing addresses
of all owners of record, as shown on the most recent property tax assessment
role, of property where the proposed pipeline is located and within 500 feet of
that property;
(g) The information
that the Department has identified in the letter described in section (2) of
this rule; and
(h) Any other
information that the Department requests as needed to make the findings
described in the applicable standards.
Notes
Statutory/Other Authority: ORS 469.405
Statutes/Other Implemented: ORS 469.405, 469.421 & 469.441
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.