Or. Admin. Code § 813-405-0035 - Program Oversight
(1) The Department
requires information from project awardees on an annual basis every year that
the fund is still actively being used for this program.
(2) Report information must include but is
not limited to the following:
(a) Number of
loan guarantees made to housing projects
(b) Entity and project information of housing
projects, including at a minimum:
(A) Lender
entity name
(B) Borrower entity
name
(C) Project location
(D) Relevant project details, including at a
minimum:
(i) Target population
(ii) Total units
(iii) Units by bedroom size
(iv) Units by rent restrictions
(c) Status of loan
guarantees made, including at a minimum:
(A)
Length of time remaining on all active guarantees and associated
loans
(B) Use of guarantees, if
applicable, by projects. Report should include both the amount activated and
how it was utilized
(d)
Construction status of project
(e)
Relevant updated financial information if necessary
(f) Pipeline of projects, if
applicable
(3)
Information review shall be done at least annually by OHCS staff and will be
delivered to the Department by, at the latest, 30 days after the end of each
fiscal year (June 30).
(a) The Department will
provide oversight to a Third Party Administrator.
(b) Oversight may be established through a
cooperative review process. Joint reviews shall be done at least annually and
may be more often if determined appropriate.
(c) The Department shall establish report
criteria for the Third Party Administrator that includes, at a minimum, the
information outlined in
813-405-0020.
Notes
Statutory/Other Authority: HB 3395 (2023)
Statutes/Other Implemented: HB 3395 (2023) & ORS 456.270 - 456.295
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.