Or. Admin. Code § 860-095-0010 - Definitions for this Division
(1)
"Advisory Forecast" means any modeling outputs created by a Qualified Regional
Program that are presented but not used as part of the Qualified Regional
Program's binding elements.
(2)
"Binding Forward Showing" means a filing used by a State Participant to show
compliance with the State Program.
(3) "Compliance Resource" means the
resource(s) or resource-specific contracts used by a State Participant to meet
the load requirements of the Binding Forward Showing.
(4) "Electric Company" has the same meaning
as ORS 757.600(11).
(5) "Electricity Service Supplier" has the
same meaning as ORS 757.600(16).
(6) "Emissions Planning Report" means a
filing made by an Electricity Service Supplier to show compliance with ORS
757.649(1)(f).
(7) "Informational Filing" means a written
explanation of a Load Serving Entity's strategy to address Resource
Adequacy.
(8) "Integrated Resource
Plan" means an Electric Company's written plan to satisfy the requirements of
OAR 860-027-0400 and Commission
Order Nos. 07-002, 07-047, and any future orders impacting filing
requirements.
(9) "Load Serving
Entity" means an Electric Company or Electricity Service Supplier.
(10) "P50 Peak Load Forecast" means a peak
load forecast prepared on a basis, such that the actual peak load is
statistically expected to be as likely to be above the forecast as it is to be
below the forecast.
(11) "Planning
Reserve Margin" means an increment of supply needed to meet conditions of high
demand in excess of the applicable peak load forecast and other conditions such
as higher resource outages, or lower availability of resources, expressed as a
percentage of the applicable peak load forecast.
(12) "Qualified Capacity Contribution" means
the portion of the nameplate capacity of a compliance resource that can be
expected to provide capacity to meet customer demand calculated using a
Commission or Qualified Regional Program approved methodology.
(13) "Qualified Parties" means Commission
Staff and Oregon Citizens' Utility Board employees who execute a modified
protective order.
(14) "Qualified
Regional Program" means a Commission-approved regional reliability planning and
compliance program that addresses Resource Adequacy through processes and
conditions established in a FERC-approved tariff.
(15) "Regional Forward Showing" means any
data, forecasts, or submittals required by a Qualified Regional Program to
support planning program compliance by a Regional Participant.
(16) "Regional Participant" means a Load
Serving Entity that is a participant in or is officially committed to becoming
a participant in a Qualified Regional Program at least 30 days prior to the
Binding Forward Showing filing date of the State Program
(17) "Resource Adequacy" means the expected
ability of a Load Serving Entity to supply aggregate electric power and energy
to meet the requirements of their consumers with a sufficient degree of
reliability and plan to meet future demand with sufficient supply-side and
demand side resource.
(18) "State
Participant" means a Load Serving Entity that is not a Regional
Participant.
(19) "State Program"
means the Resource Adequacy compliance program administered by the Commission
applicable to State Participants.
Notes
Statutory/Other Authority: ORS 183 & ORS 756