25 Pa. Code § 83.232 - Implementation and reporting
(a) The
Commission will develop financial assistance documents which will define the
terms and conditions under which the financial assistance is offered and
specify other documents determined to be necessary by the Commission.
(b) Unless otherwise approved by the
Commission, the recipient of financial assistance under this subchapter shall
begin construction of the project, in accordance with its approved application
within 9 months of the Commission sending notice of approval of a grant or loan
application. If the applicant does not begin implementation within the
specified time period, does not continue work without unreasonable interruption
or does not complete the project within the specified time period in the grant
agreement, the financial assistance may be withdrawn by the
Commission.
(c) Design and
construction of BMPs must conform to the standards found in the
Pennsylvania Technical Guide. The applicant may not
significantly deviate from the scope, design or time schedule for a project
unless prior written approval is given by the Commission or delegated agent.
The term "scope," as used in this subsection, means the extent of project
activities determined by the Commission to be eligible for financial
assistance.
(1) A request for significant
changes in scope shall be submitted in writing to the Commission for approval.
When changes in scope require a plan amendment under the criteria of §
83.371 (relating to plan
amendments), the applicant shall provide a copy of the approved plan
amendment.
(2) Funding eligibility
for a change in scope will be based on the criteria described in §
83.223 (relating to financial
assistance eligibility criteria). Consent of the Commission to a change in
scope will not be deemed to increase the amount of financial assistance
provided without the express approval of the Commission. Funding for changes in
the scope of an assistance project will be approved only in the following
circumstances:
(i) The change in scope is a
result of new or revised requirements, Federal legislation, or a Federal
regulation thereunder, State legislation or State regulation thereunder, the
act, this subchapter, The Clean Streams Law (35 P. S. §§
691.1-691.1001) or regulations
thereunder.
(ii) The change in
scope is necessary to protect the structural or process integrity of the
facilities.
(iii) Adverse
conditions are identified during the construction of the facilities which could
not have been foreseen by the design engineer prior to encountering the
condition.
(iv) The change is
necessary to relieve emergency conditions occurring during construction of the
facilities.
(d)
A request for a disbursal of financial assistance must be on forms approved by
the Commission, include a statement certifying the project was completed as
planned, and be submitted on a schedule approved by the Commission.
(e) The applicant shall maintain project
progress and financial records to substantiate expenditures, as well as plan
implementation records as outlined in §§
83.341-83.344 (relating to recordkeeping
and informational requirements).
(f)
If the applicant fails to comply with this section, the Commission may withdraw
the remaining funds allocated to the project, as well as take other action
which it is legally entitled to take.