S.D. Admin. R. 20:10:36:21 - System upgrades - Cost responsibility
The public utility shall design, procure, construct, install, and own any system upgrades. The actual cost of the system upgrades, including overheads, shall be directly assigned to the applicant or interconnection customer by the public utility.
Notes
General Authority: SDCL 49-34A-27, 49-34A-93.
Law Implemented: SDCL 49-34A-27, 49-34A-93.