S.D. Admin. R. 74:36:01:21 - Commenced construction defined

Commenced construction means the owner or operator has all necessary construction approvals or permits and has:

(1) Begun, or caused to begin, a continuous program of actual on-site construction of the new source or modification to the existing source; or
(2) Entered into a binding agreement or contractual obligation, which cannot be cancelled or modified without substantial loss to the owner or operator, to undertake a program of actual construction of the source.

Notes

S.D. Admin. R. 74:36:01:21
36 SDR 207, effective 6/28/2010.

General Authority: SDCL 34A-1-6.

Law Implemented: SDCL 34A-1-6.