(1) Engineering -
Plan documents for public water systems shall be submitted to the Department at
least thirty (30) days prior to the date on which action by the Department is
desired.
(2) Expiration of Approval
- Approval of engineering reports, proposals, preliminary plans, survey and
basis of design data shall be null and void after a period of one year from the
date stamped on the documents, unless the general and detailed plan documents
have been submitted to the Department. Approval of all other plan documents by
the Department shall be null and void after a period of one year from the date
stamped on the plan documents, unless the construction is either underway or
completed.
(3) General Practice -
All plan documents for public water system design and construction shall
present all information in conformance with accepted engineering practices and
the "Design Criteria for community Public Water Systems" as published by the
Department.
(4) Revisions to Plan
Documents - Any deviations from plan documents approved by the Department,
which affect location, sanitary and/or mineral quality, capacity, hydraulic
conditions, operating units, or the function of unit processes or distribution
and storage, must be approved in writing before such changes are made. Any
revisions must be made on the master work, i.e., the original tracings. Revised
plan documents must be submitted in time to permit the review and approval of
such revisions before any construction which will be affected by such revisions
is begun.
(5) Copies of Plan
Documents - Generally, only two copies of the engineering report and two sets
of the preliminary plans shall be required by the Department for review and/or
approval. At least four complete sets of the detailed plan documents shall be
required for final review. Upon the granting by the Department of its approval
for construction the documents shall be so stamped and two sets returned to the
engineer's office, one set forwarded to the appropriate Field Office for filing
or use in field inspection of construction, and one set retained for the
Department files. Upon completion of the project, one set of "As Built" plans
and one copy of the executed contract documents shall be submitted to the
Department and one set each to the owner. In addition, shop drawings,
instruction manuals, etc., on all equipment furnished by the project shall be
compiled into one or more documents and given to the owner.
(6) Supervision of Construction - One set of
the plan document stamped "APPROVED FOR CONSTRUCTION" shall be available at the
job sites at all times during construction. The engineer or a person qualified
other than the contractor or his representative, and approved by the public
water system shall provide continuous adequate inspection during construction
to assure that all work is done in accordance with approved plan documents. The
Department's representative shall have access to the project at any time during
construction. If the Department's representative observes work being done in a
manner that does not conform to the approved plan documents, he shall have the
authority, through the engineer's representative, the water system's agent or
directly to the contractor, to order the cessation of all work affected by the
nonconformity until such discrepancies are rectified.
(7) Engineer's Seal - Plan documents for
non-transient non-community and community public water systems shall be
prepared by a person qualified under T.C.A. §§
62-2-101
et seq. and shall have the necessary professional seal affixed as required by
T.C.A. §
62-2-306.
(8)
(a)
Ownership and Operational Organization - No person shall operate a public water
system without notifying the Division of Water Resources prior to placing the
new system in operation. Any person operating a public water system other than
an individual, a municipality, any agency or instrumentality of the United
States, any facility owned and operated by the State of Tennessee, or any
organization otherwise exempt by law must have a charter or appropriate
authorization lawfully issued as set forth in one or more of the following:
Utility District Law of 1937 - T.C.A. §§
7-82-101 et seq.
Tennessee Business Corporation Act - T.C.A. §§
48-11-101
et seq.
Tennessee Nonprofit Corporation Act - T.C.A. §§
48-51-101
et seq.
Regulation of Public Utilities by Commission - T.C.A.
§§
65-4-101 et
seq.
Urban Type Public Facilities - T.C.A. §§
5-16-101
et seq.
(b) All public water
systems shall comply with all laws, rules and regulations, and policies of the
Department. Construction modification and treatment processes must be approved
in accordance with all federally designated best available technologies and
Tennessee Laws. Every public water system shall, within thirty (30) days
following any change in ownership or operation of the system, file a written
report of such change in ownership or operation with the Department. Such
report shall, at a minimum, contain the name, home address, business address,
and home and business phone numbers of the person assuming ownership or
operation of the system, and the date such change of ownership or operation
became effective.
(c) All persons
owning or operating a public water system shall keep the Department advised of
their current address and must readily accept all mail sent to them by the
Department. For purposes of this rule, registered or certified mail sent with
proper postage to the registered owner or operator's last known address shall
be considered adequate notification regardless of whether is accepted or
returned unclaimed.
(d) Because of
the Department's statutory duty to supervise the construction, operation, and
maintenance of public water systems, and because written communication is a
necessary aspect of such supervision, an owner or operator's refusal to accept
mail or failure to claim registered or certified mail is a violation of this
Chapter and may result in enforcement action.
(9) Interconnection of Systems - Insofar as
feasible, public water systems shall be connected with a municipal, county,
regional or other existing approved water system capable of supplying the
demand. Where such connection is not feasible, other approved sources may be
considered. Each public water system shall be designed in such a manner as will
facilitate the connection of the system at an appropriate time to an expanding
municipal, county or regional system. Each public water system shall be
designed to provide service to all service areas anticipated or projected by
the owner.
(10) System Capacity -
Whenever a public water system reaches eighty (80) per cent of the design
capacity based on average day usage, the supplier of water shall immediately
obtain the services of a competent engineer to prepare plan documents for
expansion of said system.
(11)
Turbidimeters - All community water systems using ground water formations under
the direct influence of surface water, and serving more than 50 connections or
150 individuals, shall be required to install turbidity monitoring equipment
with power cutoff ability and recording unit. Those systems not included in the
above may be required to install turbidity monitoring devices if the Department
finds that the system cannot meet the microbiological standard, the turbidity
can be seen without an instrument, or there is an outbreak of illness that may
be water related. All filter plants serving community water systems shall be
required to have continuous recording turbidimeters on the filter effluent
line(s). Such instrumentation may be pen and ink, digital, computerized or
other record keeping or recording devices approved by the Department. If pen
and ink recorders are used they shall be limited to two pens and two filters
and shall use a scale of 0 to 2.0 NTU unless specific alternatives are approved
in writing by the Department.
(12)
Monitoring of new sources - All new surface or ground water sources added to an
existing water system or proposed for use by a new water system shall have the
required biological and chemical water quality monitoring completed prior to
being placed in service. The parameters to be monitored shall be those required
for drinking water for the specific type of system involved.
(13) Delegation of Plans Review Authority -
Under T.C.A §
68-221-706,
any unit of local government may petition the Commissioner for certification to
review and approve plans for water distribution facilities within its
jurisdiction. The unit of local government must have adequate experience and
expertise in water distribution and must adopt standards and impose
requirements which are at least as stringent as the Department's. The request
for certification must be in writing and contain at least the following:
(a) The names of the individual(s)
responsible for the review and approval together with his/her experience and
education. This person(s) must be employed by the unit of local government and
be a registered professional engineer in Tennessee.
(b) A copy of the standards, requirements and
design criteria legally adopted and enforceable by the unit of local
government.
(c) The type of
projects the unit of local government wishes to receive certification to
review. This may include but is not limited to water lines, distribution
pumping stations and distribution storage tanks.
(d) Procedures for maintaining records of all
projects reviewed and approved by the unit of local government.
(e) The wording to be used on the approval
stamp.
(f) Plans review authority
fee.
The Division of Water Resources will be responsible for reviewing
the application for certification and shall have up to 60 days from the receipt
of the complete application to make a written response. Units of local
government will not be certified to review projects involving state or federal
funds, raw water pump stations, new water sources, treatment facilities, sludge
handling facilities, or any project designed by the staff of the local
government. Any unit of local government which receives certification for plans
review shall submit one copy of any plan documents it has approved to the
Division of Water Resources. This shall be done within 10 days of the local
government's approval. The commissioner may periodically review the unit of
local government's plans review program and prescribe changes as deemed
appropriate. The Division of Water Resources may execute a written agreement
with a unit of local government which has received plans review certification.
Failure to comply with the terms of the agreement may result in revocation of
the plans review certification.