Tenn. Comp. R. & Regs. 1200-03-25-.03 - EXISTING SOURCE COMPLIANCE SCHEDULES
(1)
Incinerators in existence before November 6, 1988 must be in compliance, on or
before 18 month from November 6, 1988, with the standards and requirements of
this chapter. Each owner or operator of an existing incinerator shall either
demonstrate compliance with the requirements of this chapter or submit a
compliance schedule detailing the plan of action to achieve compliance within
the above 18-month time frame to the Technical Secretary within 180 days from
November 6, 1988.
(2) Individual
compliance schedules for existing incinerators approved under this rule must
contain the following increments of progress and achieve final compliance with
the specified emission standards and requirements.
(a) Date contract will be awarded
(b) Date initial construction will
commence
(c) Date construction will
be completed
(d) Date final
compliance will be achieved
(e)
Date of compliance demonstration
(3) The individual compliance schedule must
be received and approved by the Technical Secretary prior to the date of the
first increment of progress.
Notes
Authority: T.C.A. ยงยง 68-25-105 and 4-5-202.