16 Tex. Admin. Code § 78.140 - Post-Remediation Assessment and Clearance
(a)
Clearance criteria. For a remediation project to achieve clearance, a licensed
mold assessment consultant shall conduct a post-remediation assessment using
visual, procedural, and analytical methods. If walk-in containment is used
during remediation, the post-remediation assessment shall be conducted while
the walk-in containment is in place. The post-remediation assessment shall
determine whether:
(1) the work area is free
from all visible mold and wood rot; and
(2) all work has been completed in compliance
with the remediation protocol and remediation work plan and meets clearance
criteria specified in the protocol.
(b) Underlying cause of mold.
Post-remediation assessment shall, to the extent feasible, determine that the
underlying cause of the mold has been remediated so that it is reasonably
certain that the mold will not return from that remediated cause.
(c) Analytical methods.
(1) The assessment consultant shall perform a
visual, procedural, and analytical evaluation in each remediated area in order
to determine whether the mold contamination identified for the project has been
remediated as outlined in the remediation protocol.
(2) The consultant shall use only the
analytical methods and the criteria for evaluating analytical results that were
specified in the remediation protocol, unless circumstances beyond the control
of the consultant and the remediation contractor or company necessitate
alternative analytical methods or criteria. The consultant shall provide to the
client written documentation of the need for any deviation from the remediation
protocol and the alternative analytical methods and criteria selected, and
shall obtain approval from the client for their use, before proceeding with the
post-remediation assessment.
(3)
Where visual inspection reveals deficiencies sufficient to fail clearance,
analytical methods need not be used.
(d) Passed clearance report. An assessment
consultant who determines that remediation has been successful shall issue a
written passed clearance report to the client at the conclusion of each mold
remediation project. The report must include the following:
(1) a description of relevant worksite
observations;
(2) the type and
location of all measurements made and samples collected at the worksite;
(3) all data obtained at the
worksite, including temperature, humidity, and material moisture readings;
(4) the results of analytical
evaluation of the samples collected at the worksite;
(5) copies of all photographs taken by the
mold assessment consultant; and
(6) a clear statement that the project has
passed clearance.
(e)
Final status report. If the mold assessment consultant determines that
remediation has not been successful and ceases to be involved with the project
before the project passes clearance, the consultant shall issue a written final
status report to the client and to the remediation contractor or company
performing the project. The status report must include the items listed in
subsections (d)(1) - (5) and any conclusions that the consultant has
drawn.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.