37 Tex. Admin. Code § 257.4 - Required Submissions
Information
(1) Schematic design.
Documents shall illustrate the scale, relationship of project components, and
cost estimates.
(2) Design
development. Drawings and specification documents shall illustrate and describe
the size and character of the entire project as to structural, mechanical, and
electrical systems, life safety and detention locking systems, construction
materials, cost estimates, and other essentials as may be
appropriate.
(3) Construction
documents. Drawings and specification documents shall include detail
requirements for the construction of the entire project including necessary
bidding information, bidding forms, final cost estimates of construction cost,
and operation cost. These documents shall include the conditions of the
construction contract or contracts.
(4) Addendum, substitutions and changes.
Copies of all proposed addendum prepared during the bidding phase shall be
forwarded to the executive director prior to being issued. The executive
director shall respond in writing, giving approval or disapproval promptly to
the architect, not longer than ten working days after receiving the request.
Modifications, changes and all substitutions of equal material or equipment for
those specified in the approved contract documents must receive written
approval by the executive director prior to the change order or substitution
approval being issued. Emergency approval of addendum, modifications,
substitutions or changes may be sought and obtained by telephone or facsimile
from the executive director who will subsequently issue a confirming answer in
writing.
(5) Award of construction
contract. Upon award of the construction contract, the owner or the owner 's
representative shall notify the commission staff of the date construction is to
commence, estimated time of completion, and the amount of the
contract.