The applicant shall provide reports to demonstrate
progress made towards the implementation of an authorized project in accordance
with the schedule of development which shall be included in the application.
Such progress reports shall be filed in accordance with the following intervals
and contain such evidence as prescribed at each interval:
A. Twelve months following issuance.
Documentation that shows:
(i) proof of
ownership or control of site;
(ii)
the site meets all zoning and land use requirements;
(iii) architectural planning has been
initiated;
(iv) preliminary
architectural drawings and working drawings have been submitted to appropriate
state reviewing agencies and the State Fire Marshal;
(v) construction financing has been completed
or will be completed within two months and
(vi) purchase orders or lease agreements
exist for equipment and new service projects.
B. Twenty-four months following issuance.
Documentation that shows that (i) all required financing is completed; (ii)
preconstruction site work has been initiated; (iii) construction bids have been
advertised and the construction contractor has been selected; (iv) the
construction contract has been awarded and (v) construction has been
initiated.
C. Upon completion of a
project. Any documentation not previously provided which:
(i) shows the final costs of the project,
including the method(s) of financing; and
(ii) shows that the project has been
completed as proposed in accordance with the application originally submitted,
including any subsequent approved changes. See "completion" as defined in
12VAC5-220-10.
Notes
12 Va. Admin. Code §
5-220-450
Derived from
VR355-30-000 § 7.3, eff. June 30, 1993; amended, Virginia Register Volume
10, Issue 17, eff. June 15, 1994; recodified, Virginia Register Volume 13,
Issue 7, eff. January 24, 1997.