12 Va. Admin. Code § 5-220-450 - Demonstration of progress
The
A. Twelve months following issuance. Documentation that shows:
(i) proof of ownership or control of site;
(ii) the site meets all zoning and land use requirements;
(iii) architectural planning has been initiated;
(iv) preliminary architectural drawings and working drawings have been submitted to appropriate state reviewing agencies and the State Fire Marshal;
(v) construction financing has been completed or will be completed within two months and
(vi) purchase orders or lease agreements exist for equipment and new service projects.
B. Twenty-four months following issuance. Documentation that shows that (i) all required financing is completed; (ii) preconstruction site work has been initiated; (iii) construction bids have been advertised and the construction contractor has been selected; (iv) the construction contract has been awarded and (v) construction has been initiated.
C. Upon completion of a project . Any documentation not previously provided which:
(i) shows the final costs of the project , including the method(s) of financing; and
(ii) shows that the project has been completed as proposed in accordance with the application originally submitted, including any subsequent approved changes. See "completion " as defined in 12VAC5-220-10.
Notes
Statutory Authority
§§ 32.1-12 and 32.1-102.2 of the Code of Virginia.