12 Va. Admin. Code § 5-31-2910 - Amount of grant award
A.
The amount of RSAF General Grant award granted an applicant will not exceed 50%
of the cost of the item(s) except in documented and approved cases of hardship.
The amount of an RSAF General Grant award shall be based upon the amount
requested for the item(s) and state approved pricing determined by the Office
of EMS. The amount awarded will not exceed the amount requested by the
applicant.
B. Additional funding
may be recommended for those unique situations where the applicant has
demonstrated the lack of reasonable capability to generate a 50% match
(hardship). The additional funding above a 50% match will be determined by the
FARC .
1. Awards identified on the notice of
award as being "hardship" (above a 50% match level) require the grantee to
purchase from available state contracts.
Awardees, able to demonstrate the ability to purchase at a cost equal to or less than the state contract price, may purchase outside the state contract with prior approval.
2. The FARC shall recommend the percentage of
an RSAF General Grant award based upon the review of the application.
Notes
Statutory Authority
§§ 32.1-12, 32.1-111.4, and 32.1-111.11 of the Code of Virginia.
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.