12 Va. Admin. Code § 5-610-420 - Procedure for obtaining a pump and haul permit
A. An owner who seeks a pump and haul permit
shall follow the following steps:
1.
Application;
2.
Conference;
3. Plans,
specifications, and other data as may be required;
4. Securing a contract with a sewage handling
contractor having a valid sewage handling permit;
5. Submission of a detailed construction
schedule for completion of the permanent receiving facilities; and
6. Bonding.
B. Application. An application shall be made
through the district or local health department on a form provided by the
department.
C. Conference. A
conference is necessary with the district or local health department for the
purpose of discussing the reasons for pump and haul and the methods and
equipment to be utilized in the pump and haul operation.
D. Plans and specifications. Plans and
specifications in sufficient detail shall be provided, when required, to show
the sewage collection and holding facilities. See
12VAC5-610-250 C and
E for further details relating to plans and
specifications.
E. Contract with a
sewage handling contractor. The owner shall secure and maintain a contract with
a sewage handling contractor having a valid sewage handling permit. The
contract shall be for a period of time sufficient to complete the construction
necessary to alleviate the need for pump and haul.
The contract shall contain at a minimum, the following conditions:
1. Duration of
contract;
2. Pumping
schedule;
3. Availability of
equipment;
4. Emergency response
capability;
5. Disposal site,
including limitations, utilized by the contractor; and
6. The contractor shall maintain and submit
records on a monthly basis to the owner and the department. The records shall
indicate the date, time and volume of each load, the disposal site or sites
utilized and overflows or spillage.
F. Submission of detailed construction
schedules. A detailed construction schedule shall show at a minimum, initial
construction date and date of completion. Progress reports shall be submitted
monthly.
G. Bonding. The
commissioner may require any owner holding or applying for a permit issued
pursuant to this section to post a bond with surety approved by the
commissioner for the purpose of insuring continuation of the pump and haul
operation for the specified time period contained in the pump and haul permit.
Such bond shall be forfeited if the owner ceases to continue the pump and haul
operation before the need for pump and haul has been alleviated. The forfeited
bond shall be expended as necessary to restore and maintain the pump and haul
operation for the permitted time period. Forfeiture of the bond shall not
relieve the permit holder of any other legal obligations set forth in this
chapter. No bond shall be required of a government entity holding a permit in
accordance with 12VAC5-610-550.
Notes
Statutory Authority
§§ 32.1-12 and 32.1-164 of the Code of Virginia.