Wash. Admin. Code § 197-11-060 - Content of environmental review
(1)
Environmental review consists of the range of proposed activities, alternatives,
and impacts to be analyzed in an environmental document, in accordance with
SEPA's goals and policies. This section specifies the content of environmental
review common to all environmental documents required under
SEPA.
(2) The content of
environmental review:
(a) Depends on each
particular proposal, on an agency's existing planning and decision-making
processes, and on the time when alternatives and impacts can be most meaningfully
evaluated;
(b) For the purpose of
deciding whether an EIS is required, is specified in the environmental checklist,
in WAC 197-11-330 and
197-11-444;
(c) For an environmental impact statement, is
considered its "scope" (WAC
197-11-792 and Part Four of these
rules);
(d) For any supplemental
environmental review, is specified in Part Six.
(3)
Proposals.
(a) Agencies shall make certain that the
proposal that is the subject of environmental review is properly defined.
(i) Proposals include public projects or
proposals by agencies, proposals by applicants, if any, and proposed actions and
regulatory decisions of agencies in response to proposals by
applicants.
(ii) A proposal by a lead
agency or applicant may be put forward as an objective, as several alternative
means of accomplishing a goal, or as a particular or preferred course of
action.
(iii) Proposals should be
described in ways that encourage considering and comparing alternatives. Agencies
are encouraged to describe public or nonproject proposals in terms of objectives
rather than preferred solutions. A proposal could be described, for example, as
"reducing flood damage and achieving better flood control by one or a combination
of the following means: Building a new dam; maintenance dredging; use of
shoreline and land use controls; purchase of floodprone areas; or relocation
assistance."
(b) Proposals
or parts of proposals that are related to each other closely enough to be, in
effect, a single course of action shall be evaluated in the same environmental
document. (Phased review is allowed under subsection (5).) Proposals or parts of
proposals are closely related, and they shall be discussed in the same
environmental document, if they:
(i) Cannot or
will not proceed unless the other proposals (or parts of proposals) are
implemented simultaneously with them; or
(ii) Are interdependent parts of a larger
proposal and depend on the larger proposal as their justification or for their
implementation.
(c)
(Optional) Agencies may wish to analyze "similar actions" in a single environmental document.
(i)
Proposals are similar if, when viewed with other reasonably foreseeable actions,
they have common aspects that provide a basis for evaluating their environmental
consequences together, such as common timing, types of impacts, alternatives, or
geography. This section does not require agencies or applicants to analyze
similar actions in a single environmental document or require applicants to
prepare environmental documents on proposals other than their own.
(ii) When preparing environmental documents on
similar actions, agencies may find it useful to define the proposals in one of
the following ways: (A) Geographically, which may include actions occurring in
the same general location, such as a body of water, region, or metropolitan area;
or (B) generically, which may include actions which have relevant similarities,
such as common timing, impacts, alternatives, methods of implementation,
environmental media, or subject matter.
(4)
Impacts.
(a) SEPA's procedural provisions require the
consideration of "environmental" impacts (see definition of "environment" in WAC
197-11-740 and of "impacts" in WAC
197-11-752), with attention to
impacts that are likely, not merely speculative. (See definition of "probable" in
WAC 197-11-782 and
197-11-080 on incomplete or
unavailable information.)
(b) In
assessing the significance of an impact, a lead agency shall not limit its
consideration of a proposal's impacts only to those aspects within its
jurisdiction, including local or state boundaries (see WAC
197-11-330(3) also).
(c) Agencies shall carefully
consider the range of probable impacts, including short-term and long-term
effects. Impacts shall include those that are likely to arise or exist over the
lifetime of a proposal or, depending on the particular proposal,
longer.
(d) A proposal's effects
include direct and indirect impacts caused by a proposal. Impacts include those
effects resulting from growth caused by a proposal, as well as the likelihood
that the present proposal will serve as a precedent for future actions. For
example, adoption of a zoning ordinance will encourage or tend to cause
particular types of projects or extension of sewer lines would tend to encourage
development in previously unsewered areas.
(e) The range of impacts to be analyzed in an
EIS (direct, indirect, and cumulative impacts, WAC
197-11-792) may be wider than the
impacts for which mitigation measures are required of applicants (WAC
197-11-660). This will depend upon
the specific impacts, the extent to which the adverse impacts are attributable to
the applicant's proposal, and the capability of applicants or agencies to control
the impacts in each situation.
(5)
Phased review.
(a) Lead agencies shall determine the
appropriate scope and level of detail of environmental review to coincide with
meaningful points in their planning and decision-making processes. (See WAC
197-11-055 on timing of
environmental review.)
(b)
Environmental review may be phased. If used, phased review assists agencies and
the public to focus on issues that are ready for decision and exclude from
consideration issues already decided or not yet ready. Broader environmental
documents may be followed by narrower documents, for example, that incorporate
prior general discussion by reference and concentrate solely on the issues
specific to that phase of the proposal.
(c) Phased review is appropriate when:
(i) The sequence is from a nonproject document
to a document of narrower scope such as a site specific analysis (see, for
example, WAC
197-11-443); or
(ii) The sequence is from an environmental
document on a specific proposal at an early stage (such as need and site
selection) to a subsequent environmental document at a later stage (such as
sensitive design impacts).
(d) Phased review is not appropriate when:
(i) The sequence is from a narrow project
document to a broad policy document;
(ii) It would merely divide a larger system
into exempted fragments or avoid discussion of cumulative impacts; or
(iii) It would segment and avoid present
consideration of proposals and their impacts that are required to be evaluated in
a single environmental document under WAC
197-11-060(3)(b) or 197-11-305(1);
however, the level of detail and type of environmental review may vary with the
nature and timing of proposals and their component parts.
(e) When a lead agency knows it is using phased
review, it shall so state in its environmental document.
(f) Agencies shall use the environmental
checklist, scoping process, nonproject EISs, incorporation by reference,
adoption, and supplemental EISs, and addenda, as appropriate, to avoid
duplication and excess paperwork.
(g)
Where proposals are related to a large existing or planned network, such as
highways, streets, pipelines, or utility lines or systems, the lead agency may
analyze in detail the overall network as the present proposal or may select some
of the future elements for present detailed consideration. Any phased review
shall be logical in relation to the design of the overall system or network, and
shall be consistent with this section and WAC
197-11-070.
Notes
Statutory Authority: 1995 c 347 (ESHB 1724) and RCW 43.21C.110. 97-21-030 (Order 95-16), § 197-11-060, filed 10/10/97, effective 11/10/97. Statutory Authority: RCW 43.21C.110. 84-05-020 (Order DE 83-39), § 197-11-060, filed 2/10/84, effective 4/4/84.
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.