Wash. Admin. Code § 197-11-620 - Supplemental environmental impact statement - Procedures
(1) An SEIS shall be prepared in the same way
as a draft and final EIS (WAC
197-11-400 to
197-11-600 ), except that scoping
is optional. The SEIS should not include analysis of actions, alternatives, or
impacts that is in the previously prepared EIS.
(2) The fact sheet and cover letter or memo for
the SEIS shall indicate the EIS that is being supplemented.
(3) Unless the SEPA lead agency wants to
prepare the SEIS, an agency with jurisdiction which needs the SEIS for its action
shall be responsible for SEIS preparation.
Notes
Statutory Authority: RCW 43.21C.110. 84-05-020 (Order DE 83-39), § 197-11-620, filed 2/10/84, effective 4/4/84.