(1)
(a) Prior to permitting employees to start
demolition operations, a competent person must perform an engineering survey of
the structure (s) to determine the condition and structural integrity of the
framing, floors, walls, and the possibility of unplanned collapse of any
portion of the structure (s). Any adjacent structure(s) where employees may be
exposed must also be similarly checked.
(b) You must maintain a copy of the
engineering survey at the job site for the duration of the demolition
operation.
(2)
(a) You must develop and implement a written
demolition plan tailored to the operation and to the types of hazards involved.
The demolition plan must incorporate conditions of the framing, floors, and
walls, and potential of unplanned collapse of any portion of the structure(s)
identified in the engineering survey.
(b) The demolition plan must be available on
the job site for inspection by the department.
(3) You must observe federal and state codes,
safety standards, rules, regulations, and ordinances governing any and all
phases of demolition work at all times.
(4) You must conduct demolition of all
buildings and structures under the supervision of a competent person.
(5) When employees are required to work
within a structure to be demolished which has been damaged by fire, flood,
explosion, or other cause, you must shore or brace the walls or
floors.
(6) You must shut off, cap,
or otherwise control all electric, gas, water, steam, sewer, and other service
lines outside the building line before demolition work is started. In each
case, you must notify any utility company which is involved in
advance.
(7) If it is necessary to
maintain any power, water or other utilities during demolition, such lines must
be temporarily relocated, as necessary, and protected.
(8)
(a) You
must determine if asbestos, hazardous materials, hazardous chemicals, gases,
explosives, flammable materials, or similarly dangerous substances are present
at the worksite and adjacent structures that could be affected by the
demolition operation.
(b) When the
presence of any such substance is apparent or suspected, testing and removal
must be performed and the hazard eliminated before demolition is
started.
(c) Testing and removal of
such substances must be in accordance with the requirements of chapters
296-62
and
296-65 WAC, and any other applicable federal, state, or local regulations,
laws, or rules.
(9) When
the removal of material may cause dust to be formed:
(a) When the removal of material may expose
employees to airborne hazards the requirements in chapter
296-841 WAC must be
followed.
(b) When the removal of
material may expose employees to respirable crystalline silica, the
requirements in chapter
296-840 WAC must be followed.
(10) Where a hazard exists from fragmentation
of glass, you must remove such hazards prior to starting demolition
activities.
(11) You must ensure
that each employee working on, at, above, or near wall openings (including
those with chutes attached) where the outside bottom edge of the wall opening
is 4 feet or more above a lower level and the inside bottom edge of the wall
opening is less than 39 inches above the working surface, are protected from
falling by the use of a guardrail system, safety net system, personal fall
arrest system, or personal fall restraint system in accordance with chapter
296-880 WAC, Unified safety standards for fall protection.
(12) When debris is dropped without the use
of chutes, the area onto which the material is dropped must be completely
enclosed with barricades not less than 42 inches high and not less than 20 feet
back from the projected edge of the opening above. You must post signs, warning
of the hazard of falling materials, at each level. You must not permit removal
in this lower area until debris handling ceases above.
(13) Cover requirement - Holes.
(a) Hole covers must be capable of
supporting, without failure, at least twice the weight of employees, equipment,
and materials that may be imposed on the cover at any one time.
(b) You must mark each cover with the word
"hole" or "cover" to provide warning of the hazard.
(c) You must secure all covers to prevent
accidental displacement by wind, equipment, or employees.
(14) Except for the cutting of holes in
floors for chutes, holes through which to drop materials, preparation of
storage space, and similar necessary preparatory work, you must begin the
demolition of exterior walls and floor construction at the top of the structure
and proceed downward. You must remove and drop each story of exterior wall and
floor construction into the storage space before commencing the removal of
exterior walls and floors in the story next below.
(15) You must not permit workers to carry on
a demolition operation which will expose persons working on a lower level to
danger.
(16) You must protect
employee entrances to multistory structures being demolished by sidewalk sheds
or canopies, or both, providing protection from the face of the building for a
minimum of 8 feet. All such canopies must be at least two feet wider than the
building entrances or openings (one foot wider on each side thereof), and must
be capable of sustaining a load of 150 pounds per square foot.
(17) You must withdraw, drive in, or bend
over nails protruding from boards, planks or timber as soon as the same is
removed from the structure being demolished.