Wash. Admin. Code § 468-16-060 - Criteria for a determination of inability to comply with performance schedules
The following discrepancies may be cause for a determination of inability to comply with performance schedules:
(1) A majority of responses to inquiries made
to owners of previously completed projects reveal that projects have not been
completed on time; or
(2) A major
portion of projects completed within the last three years for the department
have not been completed on time; or
(3) When two or more consecutive performance
reports are rated below standard in the area of "progress of work";
or
(4) Neglectful or willful
failure to meet interim completion dates as defined in the contract.
Notes
Statutory Authority: RCW 47.01.101, 47.28.030 and 47.28.070. 93-03-020 (Order 134), § 468-16-060, filed 1/12/93, effective 2/12/93; 91-04-014 (Order 128), § 468-16-060, filed 1/28/91, effective 2/28/91.
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.