W. Va. Code R. § 170-6-17 - Negotiation When All Bids Exceed Available Funds
17.1. If all bids meeting requirements exceed
the budgeted amount, the Division may negotiate a lower price within budget
with the lowest bidder. If the negotiation does not lead to the budget amount
being met, the DAS - Purchasing Section may negotiate a lower price with the
next lowest bidder and continue negotiations with participating bidders after
negotiation closes with the preceding bidder.
17.2. Discussion and Final Offers:
17.2.1. As provided in the bid solicitation,
the Assistant Director - DAS Purchasing Section or their designee may conduct
discussions to obtain best and final offers from bidders to assure full
understanding of solicitation requirements. If the Assistant Director - DAS
Purchasing Section or their designee determines that a best and final offer is
necessary from one vendor, all vendors shall be afforded the opportunity to
provide best and final offers. All best and final offers shall be treated like
a formal bid, except that advertising is not required. All bidders shall
provide their best and final offers to the Assistant Director - DAS Purchasing
Section prior to the date and time specified.
17.2.2. Government construction contracts,
supplies and materials are exempt from this negotiation method.