W. Va. Code R. § 64-46-13 - Additional Requirements
13.1.
All installations and operations shall meet or exceed relevant requirements of
national, state, or local codes, whichever government body has
jurisdiction.
13.2. The
Commissioner shall specify construction requirements more stringent than those
specified in this rule within specific areas of concern to protect the public
health or prevent contamination of groundwater. The specific areas of concern
recommendations shall be based on the assessment of the hydrologic condition
and contaminant characteristics that may require more stringent design
standards. Prior to requiring more stringent standards within a specific area
of concern the Commissioner shall submit a report to the advisory board,
established under the Bureau's rule, Water Well Regulation, 64CSR19, section
11, for its review and recommendations.
13.3. When the strict application of any
provision of this rule presents practical difficulties or unusual hardship, the
Commissioner may grant a variance for that specific instance. Variance requests
shall be made in writing to the Commissioner on forms prescribed by the
Commissioner. The request shall include a thorough description of the site (lot
size, the location of sewers, septic tanks, buildings, seepage fields, and
other sources of contamination on the property and adjacent property with
distances shown to the proposed well) and a brief summary of the provisions for
which a variance is requested, and a complete justification as to why the
variance is needed. The requestor shall include how the alternate standard
protects the quality of groundwater and protects public health and safety. The
request shall provide a description of site-specific geologic and soil
conditions. The Commissioner shall not grant any variance unless the applicant
demonstrates that there will be unusual and unnecessary hardship in complying
with the rules; contamination of the water well will not occur as a result of
construction and operation of the system; the health of persons using water
from the private water system will not be endangered thereby; and no other
technically feasible and economically reasonable means of obtaining water from
the proposed type of water source exists. The Commissioner shall notify the
applicant in writing within thirty (30) calendar days of its decision to either
grant or deny the variance. In all cases, variances shall be approved in
advance of the performance of the actual work.
13.3.a. After any variance is issued
regarding the location of a well with respect to various contamination sources
in Table 46-46 A of this rule, the Commissioner shall take two (2) water
samples from the well and have them analyzed for Total coliform and E.
coli at an approved laboratory. The Commissioner may require analysis
for other water quality parameters that may exist in conjunction with the
source of potential pollution as necessary to protect the health or safety of
potential users. At the time the variance is approved, the Commissioner shall
notify the owner as to what these parameters are. One (1) sample shall be taken
within thirty (30) days and the second sample shall be taken within sixty (60)
days, after completion of the well. After receiving the water analysis, the
Commissioner shall determine if a water treatment unit shall be installed to
accommodate any water quality problems as determined by the chemical and
bacteriological testing.
13.3.b.
Examples of location problems which could preclude compliance with this rule
include the proposed location of a well being too close to septic tanks,
buildings, sewer lines, or barnyards as indicated in Table 64-46 A of this
rule.
13.3.c. Examples of public
health and engineering principles that may be considered in issuing a variance
are ground surface conditions, the depth of the water table, the location of
sources of pollutants, the vulnerability of the aquifer to bacteria and other
pollutants, and the geologic conditions at the site.