W. Va. Code R. § 64-92-10 - Preliminary Remediation Plan
10.1. The preliminary remediation plan shall
be submitted to the commissioner and include the following:
10.1.1. A general listing of items to be
removed from the residential property for disposal;
10.1.2. The methods used to wash hard
surfaces;
10.1.3. The sequence of
work activities;
10.1.4. Items
requiring special handling for disposal;
10.1.5. An asbestos project design, prepared
by a licensed asbestos project designer if asbestos containing materials are to
be disturbed;
10.1.6. Any obvious
safety hazards;
10.1.7. The methods
used to handle cleaning effluents generated during remediation;
10.1.8. The beginning and ending dates of the
remediation project, which may be modified only upon approval by the
commissioner;
10.1.9. The
identification of all methamphetamine remediation contractors and technicians
engaged for the project;
10.1.10.
The identification of any subcontractors to be used for any part of the
remediation project; and
10.1.11.
The identification of any waste disposal sites to be used.
10.2. Following review and approval of the
preliminary remediation plan, the Commissioner shall issue a notice to proceed
for the remediation project.
10.3.
All applicable fees set forth in Table 64-92A of this rule shall be enclosed
with a preliminary remediation plan.