Wis. Admin. Code Public Service Commission § PSC 128.33 - Political subdivision permitted provisions

A political subdivision may do any of the following in an ordinance or establish any of the following as a condition for approval of an application to construct a wind energy system:

(1) INFORMATION. Require information about whether an owner has consulted with and received any non-binding recommendations for constructing, operating or decommissioning the wind energy system from a state or federal agency, and whether the owner has incorporated such non-binding recommendations into the design of the wind energy system.
(2) STUDIES. Require an owner to cooperate with any study of the effects of wind energy systems coordinated by a state agency.
(3) MONETARY COMPENSATION. Require an owner of a wind energy system to offer an agreement that includes annual monetary compensation to the owner of a nonparticipating residence, if the residence is located within 0.5 mile of a constructed wind turbine. For one turbine located within 0.5 mile of a nonparticipating residence, the initial annual monetary compensation may not exceed $600. For two turbines located within 0.5 mile of a nonparticipating residence, the initial annual monetary compensation may not exceed $800. For three or more turbines located within 0.5 mile of a nonparticipating residence, the initial annual monetary compensation may not exceed $1,000. The initial annual monetary compensation under this subsection shall apply to agreements entered into in 2011. For agreements entered into in 2012 and thereafter, the initial annual amounts shall increase each year by the greater of two percent or the increase in the Consumer Price Index, as described in s. 196.374(5) (bm) 2 b., Stats., from the previous year. An agreement offered under this subsection shall specify in writing any waiver of a requirement or right under this chapter and whether the landowner's acceptance of payment establishes the landowner's property as a participating property under this chapter.
(3m) AERIAL SPRAYING. Require an owner of a wind energy system to offer an agreement that includes monetary compensation to a farm operator farming on a nonparticipating property located within 0.5 mile of a constructed wind turbine if the farm operator demonstrates all of the following:
(a) Substantial evidence of a history, before the wind energy system owner gives notice under s. PSC 128.105(1), of using aerial spraying for pest control or disease prevention for growing potatoes, peas, snap beans or sweet corn on all or part of a farm field located within 0.5 mile of a constructed wind turbine.
(b) A material reduction in potato, pea, snap bean or sweet corn production or a material increase in application costs on all or part of a farm field located within 0.5 mile of a constructed wind turbine as a result of the wind energy system's effect on aerial spraying practices.
(4) PERMITS. Require the owner to submit to the political subdivision copies of all necessary state and federal permits and approvals.
(5) ANNUAL REPORTS. Require the owner to file an annual report with the political subdivision documenting the operation and maintenance of the wind energy system during the previous calendar year.

Notes

Wis. Admin. Code Public Service Commission § PSC 128.33
CR 10-057: CR Register February 2011 No. 662, eff. 3-1-11.

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.