Wis. Admin. Code Public Service Commission § PSC 128.33 - Political subdivision permitted provisions
A
(1) INFORMATION. Require information about
whether an owner has consulted with and received any non-binding
recommendations for constructing, operating or decommissioning the wind energy
system from a state or federal agency, and whether the owner has incorporated
such non-binding recommendations into the design of the wind energy
system.
(2) STUDIES. Require an
owner to cooperate with any study of the effects of wind energy systems
coordinated by a state agency.
(3)
MONETARY COMPENSATION. Require an owner of a wind energy system to offer an
agreement that includes annual monetary compensation to the owner of a
nonparticipating residence , if the residence is located within 0.5 mile of a
constructed wind turbine. For one turbine located within 0.5 mile of a
nonparticipating residence , the initial annual monetary compensation may not
exceed $600. For two turbines located within 0.5 mile of a nonparticipating
residence , the initial annual monetary compensation may not exceed $800. For
three or more turbines located within 0.5 mile of a nonparticipating residence ,
the initial annual monetary compensation may not exceed $1,000. The initial
annual monetary compensation under this subsection shall apply to agreements
entered into in 2011. For agreements entered into in 2012 and thereafter, the
initial annual amounts shall increase each year by the greater of two percent
or the increase in the Consumer Price Index, as described in s.
196.374(5)
(bm) 2 b., Stats., from the previous year. An
agreement offered under this subsection shall specify in writing any waiver of
a requirement or right under this chapter and whether the landowner's
acceptance of payment establishes the landowner's property as a participating
property under this chapter.
(3m)
AERIAL SPRAYING. Require an owner of a wind energy system to offer an agreement
that includes monetary compensation to a farm operator farming on a
nonparticipating property located within 0.5 mile of a constructed wind turbine
if the farm operator demonstrates all of the following:
(a) Substantial evidence of a history, before
the wind energy system owner gives notice under s.
PSC
128.105(1), of using aerial spraying
for pest control or disease prevention for growing potatoes, peas, snap beans
or sweet corn on all or part of a farm field located within 0.5 mile of a
constructed wind turbine.
(b) A
material reduction in potato, pea, snap bean or sweet corn production or a
material increase in application costs on all or part of a farm field located
within 0.5 mile of a constructed wind turbine as a result of the wind energy
system 's effect on aerial spraying practices.
(4) PERMITS. Require the owner to submit to
the political subdivision copies of all necessary state and federal permits and
approvals.
(5) ANNUAL REPORTS.
Require the owner to file an annual report with the political subdivision
documenting the operation and maintenance of the wind energy system during the
previous calendar year.