Wis. Admin. Code Public Service Commission § PSC 130.10 - Advanced excavation work plans

Current through March 28, 2022

A municipal regulation that requires a utility to submit to a municipality its future construction or excavation work plans is reasonable in order for the municipality to coordinate work within a municipal right-of-way. It is unreasonable for a municipality to deny a permit for a utility excavation not identified on a work plan if the excavation is needed by the utility to restore service to an existing customer or to provide service to a new customer.

Notes

Wis. Admin. Code Public Service Commission § PSC 130.10
CR 01-077: CR Register June 2003 No. 570, eff. 7-1-03.