Wis. Admin. Code Public Service Commission § PSC 183.03 - Requirements for joint local water authorities before proceeding to issue bonds for a project

Current through November 29, 2021

Every authority shall submit the following information in an application for a certificate of public convenience and necessity that is required before the authority may issue bonds:

(1) A description of the project for which bonds are being issued, including a map showing proposed and existing facilities, and the location of floodplain areas.
(2) Information concerning applicable environmental factors for affected lands, such as land use zoning, forest lands, rivers, streams and wetlands.
(3) The purpose and necessity of the project, with supporting data including project start and end dates.
(4) The effect of the project on quality and reliability of service.
(5) A brief description and analysis of the alternatives to the project.
(6) The cost of the project by major plant categories or functions.
(7) The proposed method of financing the project including all terms and conditions.
(8) The estimated annual operating costs of the project, by major expense categories and functions.
(9) A description of and the original cost of any property being replaced, by major plant categories or functions.

Notes

Wis. Admin. Code Public Service Commission § PSC 183.03
CR Register, August, 1999, No. 524, eff. 9-1-99.